News ReleaseMinistry of Energy and MinesPublished: July 28, 2026

Etobicoke Greenway line adds 300 MW to western Toronto grid

A new 6.5 km, 230‑kV transmission line between Richview and Manby now supplies up to 300 MW to western Toronto, Mississauga and Oakville; finished on time and $10M under budget.

Published
July 28, 2026
Ministry
Ministry of Energy and Mines
Release type
News Release
External ID
1007807

Summary

What happened

  • The Etobicoke Greenway transmission line (230 kV, 6.5 km) was completed in late 2025 and began delivering power in March 2026.

By the numbers

  • Capacity: up to 300 megawatts (announced as enough for 300,000 homes).
  • Jobs: about 100 supported during construction.
  • Budget: project finished $10 million under budget; the savings are funding a recreational trail beside the corridor.
  • Procurement: Hydro One reported nearly all materials came from Canadian suppliers.

Where and who it affects

  • Runs between the Richview and Manby transformer stations in Etobicoke.
  • Intended to strengthen supply for western Toronto and nearby areas of Mississauga and Oakville.

Why it matters

  • Adds transmission capacity to meet rising local demand as the GTA grows.
  • Uses an existing corridor to limit new community impacts while upgrading reliability.

Other context from the release

  • The project was identified in the IESO's Toronto regional plan and is part of broader transmission work, including the planned Toronto Third Line to add further capacity.