Part IIFinal RegulationVolume 159, Number 14Published: July 2, 2025

Goldboro Tailings Area Designated

Regulations Amending the Metal and Diamond Mining Effluent Regulations: SOR/2025-138

The regulations add one geographic area near Goldboro, Nova Scotia to Schedule 2 of the Metal and Diamond Mining Effluent Regulations, designating seven small water bodies as a tailings impoundment area and enabling mine waste disposal there once a Fish Habitat Compensation Plan (FHCP) is approved. The change records a permanent loss of 0.27 hectares of fish habitat to be offset by a proposed FHCP that would create 0.54 hectares of habitat and requires a financial guarantee (about $64,000) to secure implementation.

Published
July 2, 2025
Department
Unavailable
Section
Regulations Amending the Metal and Diamond Mining Effluent Regulations
Comment deadline
Unavailable
Effective date
June 13, 2025
Publication part
Part II

Summary

Summary#

The Regulations Amending the Metal and Diamond Mining Effluent Regulations add one area near Goldboro, Nova Scotia, to Schedule 2 of the Metal and Diamond Mining Effluent Regulations. That change formally allows a proposed tailings facility to use seven small water bodies as a tailings impoundment area, resulting in the permanent loss of 0.27 hectares (ha) of fish habitat but with a planned compensation program expected to create 0.54 ha of habitat. The regulations came into force on June 13, 2025 and were published in the Canada Gazette on July 2, 2025.

What it does#

  • Lists one geographic area (about 4.5 km northeast of Goldboro, Nova Scotia) in Schedule 2 of the Metal and Diamond Mining Effluent Regulations, designating seven water bodies as a tailings impoundment area (TIA).
  • Allows mine waste to be deposited into those listed waters only after an approved fish habitat compensation plan (FHCP) is in place.
  • Records a permanent loss of 0.27 ha of fish habitat from the construction of the proposed tailings management facility (TMF).
  • Requires the project owner to post a financial guarantee to cover FHCP work estimated at $0.064 million (about $64,123 undiscounted; discounted estimate $60,207) over the FHCP schedule.
  • Notes project timing anticipated in regulatory documents: construction February 2026, commissioning 2027, operations through 2038, and start of closure 2039.

Who's affected#

  • Goldboro Gold Mines Inc. (the project proponent, subsidiary of NexGold Mining Corp) — will use the TIA for its proposed open-pit gold mine and TMF.
  • Local communities in Guysborough County, Nova Scotia, and nearby residents of Goldboro who may notice construction, traffic, or economic activity.
  • Fish and fish habitat in the area, including studies that found brook trout and American eel in some affected watercourses.
  • Indigenous groups consulted during the process, especially the Kwilmu’kw Maw-klusuaqn Negotiation Office (KMKNO), Sipekne’katik First Nation, and Paqtnkek Mi’kmaw Nation — the Sipekne’katik provided outstanding technical comments on the FHCP that were still being addressed.
  • Federal departments involved in oversight, notably Environment and Climate Change Canada and Fisheries and Oceans Canada (DFO).

Why it matters#

  • This regulatory change removes a legal barrier that previously prevented using small fish‑frequented water bodies for mine tailings. That is a key step before the mine can store tailings in the chosen TMF location.
  • The direct, permanent loss is small (0.27 ha), but the area affects real waterways and species that local people and Indigenous communities value. The proponent’s FHCP is intended to more than replace that habitat (0.54 ha planned gain).
  • A financial guarantee (about $0.064 million) must be posted to ensure the compensation work happens. The FHCP must be approved before any tailings are deposited.
  • The public record shows there was notable public interest (about 208 comments during consultation) with concerns about habitat loss and pollution risk. Indigenous consultations took place and some technical questions about the FHCP remained outstanding at the time of registration.
  • If you live nearby, use local fisheries, or follow mining and environmental issues, this change matters because it allows a major project to proceed with a government‑approved offset plan rather than requiring a different tailings location.

Key topics

Metal and Diamond Mining Effluent RegulationsMDMERSchedule 2Tailings Impoundment AreaTIAFish Habitat Compensation PlanFHCPGoldboro Gold Mines Inc.Goldboro, Nova ScotiaTailings Management FacilityTMFbrook troutAmerican eelEnvironment and Climate Change CanadaFisheries and Oceans Canada

Source: Canada Gazette