Water-well permit deadlines proposed

Summary#

HB 327, “Time Period For Produced Water Well Decisions,” would amend New Mexico’s Oil and Gas Act by adding a section on permit decisions for produced water disposal wells. Its stated goal is to require the Oil Conservation Division to decide those permit applications within set time periods. The bill is listed as introduced and postponed indefinitely, so it is not in effect.

  • The Division would have to adopt rules requiring it to review an application and tell the applicant within 30 days whether it is administratively complete (complete enough for the Division to review).
  • If an application is incomplete, the Division would have to explain in writing what information is missing. The applicant would have 30 days to file more information and could make up to two supplemental filings.
  • The review period would restart each time the Division receives a supplemental filing. If the second filing is still incomplete, the Division would have to deny the application; the applicant could submit a new one.
  • Within 15 days after an application is deemed complete, the Division would have to grant, grant with conditions, or deny the permit. If it does not act in that time, the permit would be deemed granted.
  • The bill sets decision deadlines; the supplied text does not change the substantive standards for deciding whether a permit should be granted.

What it means for you#

  • Permit applicants: You would have set periods to provide missing information, and the Division would have deadlines to assess and decide your application. If your second supplemental filing is incomplete, you would need to start again with a new application.
  • Oil Conservation Division: It would have to adopt rules requiring these steps and meet the deadlines. The bill does not set out the rules in detail.
  • People affected by a proposed well: If the Division misses the 15-day deadline for a complete application, the permit would be deemed granted even without an affirmative decision. The bill does not create a process for public notice, participation, or appeal.

Money#

No cost information is in the available material.

  • The bill requires the Division to adopt rules and meet decision deadlines, but gives no cost estimate or staffing details.
  • The supplied text does not set a fee or fine.

What is unclear#

  • The Oil and Gas Act’s current permit process was not supplied, so how these deadlines differ from current law could not be verified.
  • The bill does not define “administratively complete” or say what counts as the Division having acted on a complete application.
  • It does not specify how the deadlines are counted, or what happens if the Division’s rules are not adopted.
  • The bill does not explain how the deemed-granted permit would interact with other permits or requirements.
  • No start date is provided in the supplied text.

Case for#

  • A possible argument for the bill is that clear deadlines could make permit decisions more predictable for applicants and the Division.
  • Requiring the Division to identify missing information in writing could help applicants understand what they need to provide.
  • Allowing up to two supplemental filings, while requiring denial if the second remains incomplete, sets a limit on repeated incomplete submissions.

Case against#

  • One concern is that a permit would be deemed granted if the Division misses the 15-day deadline, even without an affirmative decision.
  • A possible trade-off is that a short deadline could leave the Division less time to assess a complete application.
  • The bill does not define when an application is complete or set out public participation or appeal steps, leaving important parts of the process unclear.