Summary#
Texas SB 395 would amend Section 382.065 of the Health and Safety Code, which concerns concrete-crushing facilities. It would require the commission, by rule, to prohibit operation within 440 yards of a hospital, as well as the other listed buildings, subject to exceptions. The stated goal is to address operation of concrete-crushing facilities near hospitals; the bill is introduced and is not law.
- The bill’s text lists single- or multifamily residences, schools, hospitals and places of worship. The distance is measured between the nearest points of the facility and the listed building.
- The prohibition would not apply to certain facilities with commission authorization in effect on September 1, 2001; facilities that met the distance rule when their initial authorization application was filed and kept that authorization; or a specified type of enclosed concrete crusher near an international border in a municipality with a population of 6,100 to 20,000.
- The bill applies to permit or permit-use authorization applications filed on or after its effective date, September 1, 2027. Earlier applications would be governed by the law in effect when filed.
What it means for you#
- Hospitals and nearby communities: If the bill becomes law, a facility covered by the rule could not operate within 440 yards of a hospital, subject to the listed exceptions. The bill does not require existing facilities to close just because a hospital is nearby.
- Concrete-crushing facility applicants and operators: New applications filed on or after September 1, 2027, would be subject to the amended law. The bill also protects a facility that met the distance requirements when its initial authorization application was filed, if that authorization is granted and maintained—even if a listed building is later established within 440 yards.
- The commission: The commission would have to prohibit the covered operation by rule. The bill does not set out application reviews, timelines or an appeals process.
- Current law: The supplied materials do not include the existing text of Section 382.065. I could not verify which parts of the listed rules and exceptions are already law and which would change.
Money#
No publicly available information on costs, savings, or funding is provided in the supplied material.
- The bill does not specify spending, staffing, fees, fines or financial assistance.
What is unclear#
- The bill does not explain how the commission would write or enforce the required rule.
- It does not define “products that contain recycled materials” or explain how the population limits for the special exception would be applied.
- The supplied material does not show how much of the amended text is new compared with current law.
- The bill does not describe how the distance requirement would interact with other permits or rules.
- Passage is uncertain; the bill has been introduced, and its stated effective date applies only if it becomes law.
Case for#
- A possible argument for the bill is that it sets a fixed separation distance between concrete-crushing facilities and hospitals, alongside homes, schools and places of worship.
- The rule would apply to later applications, while the bill protects certain facilities with existing or qualifying authorizations.
- The specified exception for enclosed crushers making products with recycled materials could allow that activity in certain border municipalities while keeping the distance rule for other covered facilities.
Case against#
- The bill applies only to applications filed on or after its effective date, so it would not generally require existing facilities to move or stop operating.
- The exceptions may leave some facilities operating within 440 yards of a hospital or other listed building.
- The bill does not explain how the commission would enforce the prohibition or handle disputes about distance and eligibility.
- Without the current text of Section 382.065, it is unclear how much the bill would change existing protections.