Summary#

H.R. 931 is a standalone bill; it does not amend an existing Act. Its stated goal is to allow federal coal to be mined under the Bull Mountains Mining Plan Modification for Federal Coal Lease MTM 97988. The bill is not law; the supplied status says subcommittee hearings have been held.

  • It would authorize mining all federal coal reserves under that lease on about 800 acres in Musselshell County, Montana, in accordance with the named mining plan modification.
  • Within 30 days after enactment, the Interior Secretary would have to approve that modification, without changing it or delaying approval, to the extent needed to mine the specified federal land.
  • The plan modification is identified as Amendment 3, which a senior Interior official approved in a November 18, 2020, concurrence memorandum.

What it means for you#

  • The federal coal leaseholder and mine operator: They would have the bill’s authorization to mine the covered federal coal under the named plan. The bill does not name the leaseholder or operator, or set out a mining schedule or amount.
  • The Interior Secretary: The Secretary would have a 30-day deadline to approve the modification as needed for mining on the specified land, and could not modify or delay that approval.
  • People near the mine and the general public: The bill does not create a new public application, review, or appeal process. It does not itself transfer federal land or lease ownership.
  • Other legal requirements: The bill does not say that other mining requirements are waived. Which requirements would still apply is unclear from the supplied material.

Money#

No cost information is in the available material.

  • The bill provides no funding amount and does not estimate administrative or staffing costs.
  • It sets no new tax, fee, or fine.
  • The required Interior Department approval may involve administrative work, but the bill gives no cost estimate.

What is unclear#

  • The bill does not explain why a further approval is needed when the plan modification had already received the 2020 concurrence memorandum, or what legal effect that memorandum has.
  • It does not define how much approval is “necessary” to mine the covered land.
  • The supplied material does not show how the bill would interact with other mining, environmental, or land-management requirements.
  • It does not identify the leaseholder or operator, or give expected production, timing, or other details of mining.

Case for#

  • The bill could give the leaseholder clearer authority to mine federal coal on the specified land under a plan already identified in an Interior Department memorandum.
  • A firm deadline and a direction not to modify or delay approval could reduce uncertainty about whether that plan can be used for mining.
  • The authorization is limited to federal coal under one lease and to the listed land, rather than applying to all federal coal.

Case against#

  • Requiring approval without modification or delay could limit the Secretary’s ability to address concerns about the plan before approving it.
  • The bill does not explain how the required approval fits with the 2020 concurrence or other applicable requirements, leaving uncertainty about what review would remain.
  • The bill gives no cost estimate or mining details, so the available material does not show the likely public expense or the scale and timing of the mining.