Executive OrderThe White HouseAugust 26, 2026

Emergency order blocks many new imports of foreign power‑grid equipment

The order bans many new transactions for foreign‑produced bulk‑power equipment in the U.S., gives the Energy Department authority to limit or remove risky devices, and sets 120–180 day deadlines.

Summary

What this does and who it affects

  • What: Declares a national emergency focused on foreign supply risks to the U.S. bulk‑power system and prohibits many new transactions involving foreign‑produced bulk‑power equipment when tied to certain foreign interests.
  • Who it affects: utilities, grid operators, vendors and installers of bulk‑power equipment, and federal energy procurement across the United States.
  • Key timelines: the Secretary of Energy must publish implementing rules within 120 days; recommend Federal Acquisition Regulation revisions within 180 days; the FAR Council has 90 days after receiving those recommendations to consider proposing changes.

Main powers and limits

  • Prohibitions: Blocks acquisition, import, transfer, or installation of foreign‑produced bulk‑power electric equipment (and related components, software, firmware, maintenance, or remote access) for transactions started after the order date when a Covered Foreign Entity has any interest and the Secretary finds an undue or unacceptable risk.
  • Authority over existing equipment: The Secretary can require identification, isolation, monitoring, securing, disconnection, replacement, or removal of previously installed equipment, with consideration for reliability and phased compliance.
  • Licensing and exceptions: The Secretary may design mitigation measures or licensing procedures to permit otherwise prohibited transactions, and may publish a list of pre‑qualified equipment and vendors; regulations, licenses, or statutes can provide exceptions.

Definitions and examples

  • "Bulk‑power system": the interconnected transmission network and generation needed for reliability; includes transmission lines rated at 69,000 volts or more.
  • Example equipment covered: substation transformers, inverters, battery energy storage systems, large and backup generators, protective relaying, industrial control systems (RTUs, PLCs, IEDs), high‑voltage breakers, metering equipment, and related software/firmware and remote access capabilities.
  • "Covered Foreign Entity": countries under an arms embargo or sanctions under ITAR or entities the Secretary (with other officials) determines pose detrimental conduct.

Reporting and implementation

  • The Secretary of Energy is authorized to adopt rules, direct cessation of prohibited transactions, order replacements, and redelegate authority within agencies.
  • Agencies must report to Congress as required under the National Emergencies Act and IEEPA.

Why it matters

  • The order focuses federal power and procurement policy on reducing reliance on some foreign‑produced grid equipment to address national‑security, resilience, and supply‑chain risks.