Corrections facilities receive capital upgrades funding

Summary#

HB 1092, the An Act For The Department Of Corrections - Division Of Community Correction Reappropriation, is an appropriation act signed into law as Act 113. It reappropriates up to $671,398 from the Community Correction Revolving Fund for capital improvements at Division of Community Correction properties and facilities. Its stated purpose is to make that funding available starting July 1, 2026.

  • The Department of Corrections may use the appropriation for maintenance, acquisition, replacement, repair, expansion, construction, equipment, renovation, purchase, improvement, or upgrades to the Division’s real property and facilities.
  • The amount is limited to the remaining balance of an appropriation made in Act 91 of 2025, and cannot exceed $671,398.
  • Contracts and other obligations cannot exceed State Treasury funds actually available. The Department may also use grants and donations, including federal funds, and available cash income or other funds to supplement project costs.
  • The act bars using the agency’s Maintenance and General Operations appropriations for these capital-improvement purposes. Other state fiscal-control laws still apply.

What it means for you#

  • Department of Corrections – Division of Community Correction: The Department can draw on the reappropriated funds for the listed facility and property work, subject to the funding limit and fiscal controls. The act does not require that the full amount be spent.
  • People who use or live near these facilities: The act does not directly change sentences, supervision rules, eligibility for services, or access to community-correction programs.
  • The public: The act authorizes funding for specified facility work; it does not create a new tax, fee, fine, or benefit.

Money#

The act appropriates up to $671,398 from the Community Correction Revolving Fund; it does not give an estimate of actual spending.

  • The appropriation is limited to the balance of the earlier Act 91 of 2025 appropriation, up to the stated maximum.
  • The act allows grants, donations, federal funds, and available cash income or other funds to supplement project costs.
  • It does not state how much will be spent on each project or how many staff, if any, will be needed.

What is unclear#

  • The supplied material does not include Act 91 of 2025, so I could not verify what it originally authorized or how much of its appropriation remains unspent.
  • The act does not list specific projects, locations, or amounts for each type of work.
  • The act does not set out a project-selection process, completion dates, or a reporting schedule.
  • The law ties spending to reasons in budget materials and legislative records, but those materials were not supplied.

Case for#

  • The act appears intended to keep funding available for repairs and other capital work at Division facilities starting July 1, 2026.
  • Reusing the remaining balance of an earlier appropriation could allow those projects to proceed without creating a new appropriation for more than the stated maximum.
  • State fiscal controls and the limit on obligations to funds actually available provide safeguards against committing more money than is available.

Case against#

  • The act allows a broad range of work on real property and facilities, but does not identify which projects will receive the money or how the Department will choose among them.
  • Without the earlier Act 91 or project-level information, the public cannot tell how much of the $671,398 is actually left or what work it may fund.
  • The amount is an authorization, not a spending estimate; actual costs and any additional funds used are not stated.

Votes

The recorded vote on this bill, member by member.

  1. Division No. 1687631

    Passed97 members voted

    Third Reading

    FOR · 97

    97For

    • Republican77
    • Democratic20

    0Against

    2 members were paired and sat out the vote.