Summary#

Introduction 45-2026, sponsored by Council Member Joann Ariola, would create a local-law requirement for the Director of Long-Term Planning and Sustainability to study infrastructure risks in flood risk areas. Its stated goal is to assess risks linked to more frequent flooding and residential development; it is not yet law and is waiting in committee.

  • The director, consulting with relevant city agencies or offices, would have to create a risk-scoring system and score at least 10 contiguous zones that together cover the entire flood risk area.
  • For each zone, the director would have to score four levels of possible residential development, from the maximum permitted by zoning to increases of 75%, 50%, and 25% over current development.
  • The study must consider infrastructure condition, past flood-related service disruptions, likely effects of sea-level rise and flooding, and likely effects of future residential development. The director may consider other factors too.
  • Within 24 months after the law takes effect, the director must send the study to the Mayor and Council Speaker and publish it on the office’s website. The bill would take effect immediately if enacted.

What it means for you#

  • Residents and property owners: The bill would not directly change zoning, require construction, or guarantee protection from infrastructure disruptions. It requires a study.
  • City government: The director must conduct and publish the study, in consultation with relevant city agencies or offices. The bill does not require residents or businesses to apply or provide information.
  • Flood-risk areas: The bill uses the flood-risk-area definition in the Administrative Code, including coastal and 10-year rainfall flood risk areas. The code text is not included here, so that definition cannot be checked against the current code.

Money#

No cost information is in the available material.

  • The bill requires the director to conduct and publish a study, but gives no estimate for staff time, agency support, or other costs.

What is unclear#

  • The bill does not set out how the director must calculate scores, or what each score would mean in practice.
  • It does not specify how the director should measure the different development levels against current residential development.
  • It does not require public input, independent review, updates to the study, or city action in response to the scores.
  • The bill does not say how the study would account for infrastructure that serves areas beyond a scored zone.

Case for#

  • A possible argument for the bill is that scoring risks across the full flood risk area could help the city identify where flooding and future residential development may put infrastructure services under strain.
  • Requiring the study to consider infrastructure condition, past disruptions, flooding, and several development scenarios could make the assessment more comprehensive.

Case against#

  • One concern is that the bill requires scores but does not define a scoring method or explain how the scores would guide city decisions.
  • The study could require staff time and coordination across agencies, but the bill gives no cost estimate or funding source.
  • The bill requires publication, but does not require the city to take action based on the findings.