Requiring the department of buildings to notify building owners about emergency demolitions

Summary#

Int. 332, introduced by prime sponsor Council Member Mercedes Narcisse, is a proposed local law amending the New York City Administrative Code. It would require the Department of Buildings (DOB) to notify owners when the department determines that a structure must be demolished under the emergency-demolition section of the Code. Its stated purpose is to inform owners about the demolition; the bill is waiting in committee and is not law.

  • The DOB commissioner would have to send the owner written notice as soon as practicable after making that determination.
  • The notice must state why demolition is needed, its approximate start date, the owner’s responsibility to pay, an estimate of the cost, and the phone number and email address of a DOB employee knowledgeable about the procedures. The commissioner may include other information.
  • If enacted, the local law would take effect 90 days after it becomes law.

What it means for you#

  • Owners of structures marked for emergency demolition: You would be entitled to the specified written notice. The bill does not require that notice arrive before demolition begins.
  • Other residents and the public: The bill does not change the stated grounds or process for deciding that a demolition is required.

Money#

No publicly available information gives the cost to DOB of preparing and sending notices.

  • The notice must include an estimate of demolition cost and state that the owner is responsible for paying. The bill does not set a fee or fine.
  • The bill text does not establish a new payment duty; the current Code provision it refers to was not supplied, so existing payment liability could not be verified.

What is unclear#

  • The current text of the emergency-demolition section was not supplied, so how the bill would interact with existing rules could not be checked.
  • “As soon as practicable” is not defined. The bill does not require advance notice, a reply period, or a way to challenge the decision or cost estimate.
  • The bill does not say how the cost estimate must be calculated or whether owners would receive an updated estimate.

Case for#

  • The bill’s required notice would give affected owners the reason for demolition, an approximate start date, a cost estimate, and a contact at DOB. That information could help them understand what is happening and whom to contact.

Case against#

  • The bill does not ensure that owners receive notice before demolition starts, and it creates no process to question the decision or estimate.
  • It requires DOB to tell owners they are responsible for payment, but the available materials do not clarify how that statement fits with the existing Code rules.