Summary#
Introduction 0658-2026, sponsored by Council Member Inna Vernikov, would amend New York City’s Administrative Code. It would require the Department of Buildings (DOB) to perform final inspections for defined major solar energy projects; the bill’s stated goal is to make DOB responsible for those inspections. It has only been introduced and referred to committee, so it is not law and is waiting in committee.
- A project would count as “major” if it installs a solar photovoltaic system with a nameplate capacity of at least 25 kilowatts direct current, or alters a system so added equipment brings its total capacity to that level.
- Under current code, final inspections for work that does not need a certificate of occupancy are generally performed by an approved agency on the owner’s behalf, or by DOB as directed by the commissioner. The bill would make DOB perform them for major solar projects.
- The applicant would still have to take all reasonable and necessary steps to ensure the inspection happens within one year after the last permit expires. The inspection would take place after permitted work is complete.
What it means for you#
- Solar project applicants and owners: For projects meeting the bill’s threshold, DOB—not an approved agency—would perform the final inspection. The bill does not change the one-year deadline for ensuring the inspection occurs.
- Owners of smaller solar projects: The new requirement would not apply unless an installation or alteration meets the stated capacity threshold.
- General public: The bill would not directly change solar incentives, project approval rules, or the existing requirements for correcting defects found in an inspection.
Money#
No cost information is in the available material.
- DOB would have to perform the new inspections, but the bill gives no staffing or cost estimate.
- The text does not set a fee for these solar inspections. It separately retains a fee for a different existing category of inspection.
What is unclear#
- The bill does not say how DOB would schedule inspections or what happens if it cannot complete one within the one-year period.
- It does not specify whether applicants or owners would pay any fee for a major solar project inspection.
- The bill does not provide an estimate of how many projects would meet the threshold or how much additional work DOB would face.
Case for#
- A possible argument for the bill is that having DOB perform these inspections could give the department direct responsibility for checking major solar work against approved plans and applicable rules.
- The bill uses a capacity threshold, so the new requirement would focus on larger installations and alterations rather than all solar projects.
Case against#
- One concern is that the bill requires DOB to take on these inspections without specifying added staff, funding, or how inspection delays would be handled.
- The bill does not explain why this threshold is the right dividing line or how the new inspections would fit with the existing final-inspection process.