Summary#
Introduction 0770-2026, sponsored by Public Advocate Jumaane Williams, would amend the New York City Building Code. Its stated goal is to strengthen scaffolding requirements by narrowing exceptions that allow a competent person, rather than a licensed rigger, to supervise certain suspended-scaffold work. It was referred to committee on March 10, 2026, and is not law.
- For façade alteration, maintenance, or repair on a major building where a site safety plan is required, the bill removes an exception allowing a competent person to supervise suspended-scaffold installation and removal.
- It also removes the exception allowing a competent person to supervise use of a suspended scaffold for that façade work.
- The exceptions would remain for work done with construction of a new building, full demolition of an existing building, or vertical or horizontal enlargement of an existing building.
- The Department of Buildings commissioner must take implementation measures, including making rules, before the law takes effect 120 days after it becomes law.
What it means for you#
- Building owners and construction businesses: For the specified façade work, they could no longer rely on these exceptions to use a competent person instead of the supervision described in the underlying Building Code. The bill does not reproduce the underlying rules, so the precise requirement after the exceptions are removed cannot be confirmed from the supplied text.
- Scaffold permit holders and controlling entities: The bill removes their ability to designate a competent person under these exceptions for the specified façade work.
- Licensed riggers and competent persons: The exceptions would still allow competent-person supervision for the three listed types of building work, but not for the specified façade work.
- Others: The bill does not create a new permit, application, inspection, or appeal process.
Money#
No publicly available information on estimated costs.
- The bill requires the Department of Buildings commissioner to take implementation measures, including making rules, but gives no staffing or cost estimate.
- It does not set a fee, fine, or appropriation.
What is unclear#
- The underlying Building Code is not supplied, so the exact supervision rules that would apply once these exceptions are removed cannot be verified.
- The bill does not define “competent person” or explain how the Department of Buildings will implement the change.
- No committee name, hearing, or vote is listed in the supplied history.
Case for#
- The Council’s summary says the bill would reduce situations where someone other than a licensed rigger can install, remove, or supervise the use of scaffolding.
- A possible argument for the bill is that requiring the underlying Code’s supervision rules for the specified façade work could strengthen oversight.
Case against#
- One concern is that removing the exceptions may require different or more extensive supervision for this façade work; the bill provides no estimate of added costs or staffing needs.
- The bill does not explain why this façade work is treated differently from the three types of building work where competent-person supervision remains allowed.