Summary#
Introduction 817-2026 would amend the New York City Administrative Code. Prime sponsor: Council Member Oswald J. Feliz. Its stated goal is to promote coordination and efficient scheduling of construction on capital projects. It has been introduced and referred to a committee; the committee name is not stated in the available history.
- Each agency responsible for a capital project’s functions and operations would have to prepare a monthly report for projects that are or will be in the construction phase during the reporting period.
- Reports would list work planned for the next three months, with its location, description and scheduled dates, and give the status of work listed in the previous six reports. They must include locations, descriptions and dates for completed work, and explain missed or unfinished work where applicable.
- The Mayor, or a designated office or agency, would have to compile the reports into a citywide report, review it to promote coordination, and send it to the Council Speaker and specified utility and infrastructure entities. The report must also be posted online in a non-proprietary format that can be processed automatically and downloaded in bulk.
What it means for you#
- City agencies: Managing agencies and their heads would have to prepare and submit the reports. The bill does not give contractors, utilities or residents a new reporting duty.
- Utilities and the public: Gas and electric service providers and entities with a City franchise to build and maintain subsurface electrical conduit and manhole infrastructure would receive the citywide report. The public would be able to download it from the City website.
- Timing: If enacted, the law would take effect 120 days after it becomes law. It is not law now.
Money#
No cost information is in the available material.
- The bill would require agencies to prepare reports and the Mayor or a designee to compile and review them, but it gives no staffing or cost estimate.
What is unclear#
- The bill does not define the “reporting period” or set a specific monthly submission date.
- It does not say how the Mayor’s office would address missing, inaccurate or conflicting agency information.
- The current Administrative Code was not supplied, so I could not verify whether related reporting duties already exist.
- The bill does not specify how the citywide review would lead to changes in project schedules.
Case for#
- The bill says the citywide report would be reviewed to promote coordination between managing agencies and efficient scheduling. Bringing project schedules and updates together could help agencies and utility entities see planned work in the same locations.
- Requiring explanations for work that was not conducted or completed as scheduled could make schedule changes more visible.
Case against#
- One concern is that monthly reporting and citywide compilation would take agency time, but the bill gives no cost or staffing estimate.
- The bill does not set submission deadlines or explain how the review would resolve scheduling conflicts, which could limit how useful the reports are for coordination.