Trade waste management and disposal for construction, alterations, and demolition

Summary#

Int. No. 899, sponsored by Council Member Ty Hankerson, would amend the New York City Administrative Code. It would require construction-waste plans and proof of compliance before certain permits are signed off; its stated goal is to ensure trade waste from construction, alteration and demolition is properly disposed of. The bill was laid over in the Sanitation and Solid Waste Management Committee on May 19, 2026, and is waiting in that committee.

  • Permit applicants for new buildings and for alterations or demolitions would have to file a plan covering estimated waste, licensed haulers, receiving facilities and transport routes. The plan could be amended.
  • Before permit sign-off, the permit holder would have to submit proof of compliance, such as hauler receipts and facility manifests. The Department of Buildings (DOB), with the Department of Sanitation and Department of Environmental Protection, would have to verify compliance.
  • A violation of the plan requirement would carry a minimum $1,000 civil penalty.
  • Repeated failure to follow a plan would become a ground for licensing action: the relevant commissioner could deny, suspend or revoke a license under one provision; DOB’s commissioner could suspend or revoke a license or certificate, impose a fine of up to $25,000 per finding, or order repairs under another.
  • The bill would take effect immediately if enacted. It is not law now.

What it means for you#

  • Construction and demolition permit applicants: You would have to identify licensed haulers, receiving facilities and routes, and estimate the waste the work will generate.
  • Permit holders: Before sign-off, you would have to provide documents showing compliance. The bill does not require all waste to be recycled; it allows plans to identify disposal or recycling facilities.
  • Licensed haulers and receiving facilities: They are named in the plan and verification requirements, but the bill does not set separate duties or standards for them.
  • Contractors and license holders: Repeated failure to follow a plan could put a license or certificate at risk. The bill does not create a new front-line waste collection service.

Money#

No publicly available information on public costs, savings or revenue is provided.

  • The bill requires DOB and two other city departments to verify compliance, but gives no staffing or cost estimate.
  • Applicants and permit holders would need to prepare plans and provide records; the bill gives no estimate of those costs.
  • A plan violation would carry a minimum $1,000 civil penalty. The text also adds repeated plan failures as grounds for licensing action, including a possible fine of up to $25,000 per finding under DOB’s authority.

What is unclear#

  • The bill does not define what counts as a “practice or pattern” of failing to follow a plan.
  • It does not set standards, timelines or a process for the departments’ verification, or explain what happens if they do not verify compliance before sign-off.
  • It does not say how violations are counted for the $1,000 minimum penalty.
  • It does not explain how the new requirements would interact with other waste or permit rules.

Case for#

  • The Council summary says the bill is meant to ensure construction-related trade waste is properly disposed of.
  • A plan naming haulers, destinations and routes, followed by receipts and facility records, could give the city a way to check whether waste was handled as planned.
  • Adding licensing consequences for repeated failures could give the plan requirement more force.

Case against#

  • One concern is that applicants and permit holders would have to prepare plans and records, while the bill leaves key details of verification and compliance unclear.
  • The bill does not define repeated failure, leaving uncertainty about when licensing action would be justified.
  • The bill requires identifying disposal or recycling facilities, but does not require recycling or set a waste-reduction target.