Public Infrastructure Faces Higher Rainfall Standards

Summary#

HB 1356 would add two sections to the Virginia Code: one setting precipitation rules for state transportation projects and one applying standards to public infrastructure statewide. Its stated goal is to account for observed and projected increases in rainfall intensity, frequency, and duration when infrastructure is designed. The bill is introduced and not law; passage is uncertain.

  • The State Water Control Board would lead in setting and maintaining precipitation design standards, using the latest NOAA precipitation-frequency estimates and choosing the projection period.
  • State agencies and local governments would have to use climate-adjusted precipitation values when setting design standards for stormwater facilities, floodplain management, culverts, bridges, and other public infrastructure, including public-private partnership projects.
  • Until NOAA Atlas 15 estimates are published and adopted by Virginia, the Board would have to issue guidance requiring NOAA Atlas 14 values to be increased by at least 20% for design.
  • The Board would review related stormwater rules and technical criteria at least annually. It could adopt standards or issue guidance through an abbreviated process.
  • The Department of Transportation (VDOT) would have to use the standards for transportation infrastructure and update relevant manuals. The Board and VDOT would have to identify funding sources; VDOT must also pursue them.
  • Localities could adopt stricter standards for local or regional flood risks. Relevant state agencies must update manuals and standards by July 1, 2027, and updated standards must take effect no later than that date.

What it means for you#

  • State agencies and local governments: They would have to use climate-adjusted rainfall values when setting design standards for covered public infrastructure. Localities would also have to bring their stormwater design manuals and standards into line with the bill.
  • VDOT: It would have to apply the standards to transportation infrastructure, update relevant manuals and specifications, coordinate with other agencies, and pursue available funding.
  • People who use or live near public infrastructure: New or changed infrastructure designs could use higher rainfall values. The bill does not order retrofits of existing infrastructure or promise a particular flood-risk reduction.
  • The public: The bill assigns the lead role to the existing State Water Control Board; it does not create a new independent agency or a direct public benefit program.

Money#

No cost estimate or appropriation is provided in the bill materials.

  • The Board and VDOT would have to identify funding sources; VDOT would also have to pursue them. The Board could enter contracts and agreements to receive funding.
  • The bill does not state how much implementation, staffing, construction, or maintenance would cost, or how much funding would be obtained.

What is unclear#

  • The bill does not define “climate-adjusted precipitation values” or specify the projection period the Board must choose.
  • It does not set out a detailed process for choosing standards, involving the public, or reviewing the Board’s decisions.
  • It does not explain how the 20% increase based on Atlas 14 would work alongside the requirement to use the latest NOAA estimates, or how long the interim guidance would apply.
  • The materials do not include the current Code sections or related rules, so it is not possible to verify which requirements already exist or exactly how the bill would change them.
  • It is unclear what funding or staff would be available and how the required updates would be paid for by the July 1, 2027 deadline.

Case for#

  • A possible argument for the bill is that infrastructure designed around older rainfall estimates may not account for changing precipitation conditions.
  • Using a common statewide standard could help agencies and local governments base infrastructure designs on the same updated estimates.
  • Annual review could give the Board a regular way to check whether the technical criteria remain suitable.
  • The option for localities to use stricter standards would leave room to respond to local or regional flood risks.

Case against#

  • One concern is that the bill sets a 20% increase as an interim minimum without explaining in the text how that figure should be applied across different projects or locations.
  • The Board would choose the projection period and lead the standards process, but the bill gives few details about public input or how decisions could be challenged.
  • The July 1, 2027 deadline could require substantial technical and manual updates, while the bill provides no cost estimate or specific funding.
  • The bill does not explain how the statewide standards would interact with existing local or state rules.