Lien Filing Deadline Would Extend

Summary#

HB 752, titled “Mechanics’ liens; liens attaching to property, memorandum of lien,” would amend Virginia Code sections on mechanics’ liens. Its main apparent change is to extend the deadline for filing a memorandum of lien from 90 to 120 days. The bill does not state a separate goal or promise a particular result.

  • The longer deadline would apply to general contractors and other lien claimants covered by the cited code sections.
  • The filing deadline would still be measured from the last day of the month in which labor or materials were last provided, and there would still be an outside deadline tied to when the project is completed or the work ends.
  • The proposed text retains a 150-day limit on how far back a memorandum can claim amounts for labor or materials, with exceptions for certain retainage and amounts not yet due.
  • A lien would not arise automatically: the claimant would still have to meet the requirements for perfecting one, including filing a memorandum.
  • The bill also re-enacts provisions on who may claim a lien and whose interest in land may be subject to one. The supplied material does not show whether those provisions would change current law.

What it means for you#

  • Contractors and other lien claimants: If enacted as shown, you would have 30 more days to file a memorandum of lien. The proposed text still requires the memorandum to identify the owner and claimant, state the claim and describe the property. General contractors would also have to file certification that they mailed a copy to the owner.
  • Property owners: A lien claim could be filed later than under the apparent current 90-day deadline. The bill would not itself place a lien on a property; a claimant would still need to meet the legal requirements and file.
  • People buying or improving property: The proposed text says recording costs are taxed against the person found liable in a judgment enforcing the lien. The supplied material does not show whether that rule would change.
  • Other groups: No direct change for workers, tenants, or the public is stated in the supplied text.

Money#

No cost information is in the available material.

  • The bill includes no appropriation or cost estimate.
  • The proposed text assigns recording costs in a lien case to the person found liable in a judgment, but does not show whether this is a new rule.

What is unclear#

  • The supplied material does not include the current Code sections or a clean comparison with current law. The displayed “90 120 days” appears to mean replacing 90 days with 120, but the full extent of changes to the re-enacted sections cannot be verified.
  • The material gives no start date, fiscal estimate, or information on how many claims might be affected.
  • It is unclear whether the bill would change any other part of the lien rules beyond the apparent filing-deadline change.
  • The supplied status says the bill is introduced and was continued from the last session. It is not law, and whether it will pass is uncertain.

Case for#

  • A longer filing period would give claimants more time to record a lien after providing labor or materials.
  • This could reduce the chance that a claimant loses the ability to seek a lien solely by missing the apparent 90-day deadline.
  • The bill would extend the deadline without removing the filing requirement or the stated 150-day limit on the age of most claimed amounts.

Case against#

  • Property owners could face uncertainty about potential lien claims for an additional 30 days.
  • A longer filing period may delay certainty about whether a lien will be claimed against a property.
  • The supplied material does not explain why 120 days is the right period or give information about the likely effects on claimants and owners.