Part INoticeVolume 160, Number 21Published: May 23, 2026

Neradean Seeks U.S. Electricity Export Permit

Canada Gazette, Part I, Volume 160, Number 21: COMMISSIONS

Neradean Energy Inc. applied on March 5, 2026 for authorization to export up to 200,000 MWh of electricity per year to the United States for 10 years under the Canadian Energy Regulator Act. The Commission of the Canada Energy Regulator is accepting written comments on the application (due June 22, 2026) and seeks views on provincial impacts and whether Canadian buyers were given a fair opportunity to purchase the electricity.

Published
May 23, 2026
Department
Unavailable
Section
CANADA ENERGY REGULATOR
Comment deadline
June 22, 2026
Effective date
Unavailable
Publication part
Part I

Summary

Summary#

  • Neradean Energy Inc. applied to the Canada Energy Regulator on 5 March 2026 to export electricity to the United States.
  • The company seeks approval to export up to 200,000 MWh per year for 10 years, and the regulator is asking the public for input before deciding.

What it does#

  • Asks the regulator to allow an export of up to 200,000 MWh of electricity each year for 10 years.
  • The application was made under Division 2 of Part 7 of the Canadian Energy Regulator Act.
  • The Commission of the Canada Energy Regulator is inviting written comments from interested parties about the application. Key deadlines:
    • Written submissions are due by June 22, 2026.
    • The applicant may file answers to submissions by July 7, 2026.
  • The Commission specifically wants views on:
    • How the export could affect provinces other than the one supplying the electricity.
    • Whether the applicant told those who declared interest in buying power in Canada about the quantities and types of service available, and whether those buyers were given a fair chance to buy on comparable terms.
  • The application is publicly available on the CER website, and Neradean Energy Inc. will provide a copy by email on request.

Who's affected#

  • Neradean Energy Inc. (the applicant) and the Canada Energy Regulator (the decision-maker).
  • Electricity buyers and sellers in the parts of Canada linked to the export route — including utilities, large industrial customers, and provincial grid operators.
  • The notice asks for views from any interested parties; it is not clear from the notice which specific provinces or communities would be most affected.

Why it matters#

  • Approving the export would let a private company send a significant amount of electricity out of Canada for a decade.
  • That can matter for local markets and grid planning: it could affect who gets access to power and on what terms, and regulators need to check whether Canadian buyers had a fair chance to buy the same energy.
  • The Commission’s public comment step is the chance for utilities, governments, and others to raise concerns about supply, prices, or regional impacts before a permit or licence decision is made.

Key topics

Canadian Energy Regulator ActCERDivision 2 of Part 7Neradean Energy Inc.Canada Energy RegulatorCommission of the Canada Energy Regulatorelectricity exportcross-border electricity200,000 MWh10 yearsexport permitpublic consultation

Source: Canada Gazette

Official source