Ottawa sends Whitehorse power plan to Major Projects Office

The proposed project would add power capacity in stages, starting with 15 megawatts by 2028 to help meet the Yukon’s winter electricity needs.

Summary

The Major Projects Office will help the Yukon assess the proposed Whitehorse Power Centres project, including grid upgrades, electricity demand, fuel types, locations and investment opportunities for Indigenous partners and the private sector.

  • Initial phase: Two thermal power plants, a substation and transmission infrastructure are proposed to add 15 megawatts by 2028.
  • Later phases: Could add capacity up to about 150 megawatts.
  • Federal support: Up to $73 million through the Build Communities Strong Fund.

The project is intended to provide reliable power during winter peaks and support growing communities and industries. The release says Yukon homes and businesses connected to the grid use about 80% of Yukon Energy’s available power on an average winter day, rising to around 90% during cold snaps.