There was no objection.
The Clerk read the title of the bill.
Sam Graves (R-MO)11:24 a.m.
Mr. Chairman, I yield myself such time as I may consume.
Mr. Chair, I am proud to rise in support of H.R. 3898, the Promoting Efficient Review for Modern Infrastructure Today Act, or the PERMIT Act, which will make permitting processes under the Clean Water Act more efficient, consistent, and transparent while continuing to protect our Nation's water quality.
Our Clean Water Act permitting regime is broken.
When it takes up to 18 months to receive a permit under just the Clean Water Act to build a pipeline, dam, road, pond, or home, something is simply wrong.
When wastewater utilities are being sued by radical environmentalists because the EPA didn't give them a permit they could trust, something is wrong.
When one State can weaponize the Clean Water Act to stop a pipeline that would allow citizens in other States to move off heating oil in the winter to a cheaper and more reliable source of energy, for reasons not remotely related to water quality, something is wrong.
When the Federal Government is allowed to write water quality standards that no one can afford without passing on costs to the ratepayers, or for which the technology to achieve such standards isn't even available in this country, something is wrong.
I believe that regulations should be simple to understand, achievable, and easy to follow. Good process often leads to good decisionmaking, more consistent outcomes, and prosperity, and that is what this bill seeks to achieve.
The partnership between the private sector, States, and the Federal Government envisioned by the Clean Water Act has worked to improve water quality nationwide. This is a very good thing. We all share the goal of achieving clean water. However, 50 years after its passage, the Clean Water Act needs modernization. It is just as simple as that.
This bill makes commonsense reforms, such as clarifying the section 401 process to stop it from being weaponized; codifying longstanding, bipartisan exemptions from the definition of waters of the United States; placing clear timelines on judicial review for permits; and increasing transparency in the development of water quality standards.
It also directs the Corps to eliminate the backlog of outstanding section 404 permit applications and jurisdictional determinations and eliminate duplicative and unnecessary permitting processes for areas such as pesticides, aerial fire-retardant use, and so much more.
The bottom line is that without reforming the Clean Water Act, America cannot efficiently build roads, bridges, pipelines, ponds, dams, levees, airports, homes, farms, and other infrastructure that we need.
This bill acknowledges that we can both protect our natural resources and allow for development that benefits everyone in this country. Because of this, H.R. 3898 enjoys support from a wide range of stakeholders, from water utilities to energy developers, the construction industry, farmers, and Main Street businesses.
I urge my colleagues who support commonsense solutions to vote in favor of H.R. 3898.
Mr. Chair, I reserve the balance of my time.
Rick Larsen (D-WA)11:30 a.m.
Mr. Chair, I thank Representative Scholten for yielding time.
Mr. Chair, I rise today to oppose the dirty water act. This bill will make it more difficult to keep our water clean and will, ironically, add more uncertainty to the permitting process, just the opposite of what we need to have happen. This bill guts Federal, State, Tribal, and local authority and resources to attain clean water and protect locally important water bodies.
First, this bill significantly restricts Federal oversight and regulatory authorities under the Clean Water Act. The current administration has already acted to slash Federal funding for clean water and eliminate agency staff. This bill compounds those efforts and will leave Federal agencies powerless to fulfill their responsibilities under the Clean Water Act.
Second, the bill undermines the partnership that the Federal Government has with States and Tribes to prevent pollution, weakening States' and Tribes' ability to better protect their own water. The result will be more pollution in our Nation's rivers, streams, and lakes, thanks to loopholes, legal shields, and limited oversight of polluters.
Third, this bill will end up slowing projects by increasing regulatory uncertainty and delay. Democrats want to pass bills that invest in infrastructure and get projects done faster. That is why we passed the bipartisan infrastructure law. It invested in all types of infrastructure for communities nationwide. Fully funding projects and the Federal agencies charged with approving them is the quickest way to get this infrastructure built.
Instead, this bill, when paired with efforts to cut funding, as well as other Federal water infrastructure programs, will slow down investments in cleaner, greener, safer, and more accessible State and local projects.
Under this bill, communities of all sizes will end up with dirtier water and be left with the cost of cleanup. This will hurt rural communities and minority communities. It will hurt them especially hard, as well as other communities struggling financially under the policies of the current administration.
This bill shifts the cost of pollution from polluters to American families who will have to spend more for safe drinking water and access to water-related recreational areas if such resources are even still available.
Members of this committee on a bipartisan basis have supported predictability in regulating clean water, and there is another way. We don't have to choose between clean water and a robust economy. We can have both. My State is a great example. It is defined by its clean water, including the Puget Sound and hundreds of lakes and thousands of miles of rivers and streams throughout Washington.
We all know that rivers, streams, and wetlands are intrinsically connected. The health of the waters in my State and its water-related economy depend upon a strong partnership with the Federal Government and a level playing field among its upstream users and downstream neighbors, including local Tribal communities.
During the consideration of this bill in the committee, my Democratic colleagues offered several amendments to fix the loopholes, liability shields, and limited oversight for polluters contained in this bill. These amendments targeted the most egregious provisions of this bill, not every provision of the bill.
It targeted provisions that eviscerated Federal and State clean water agencies; provisions that made it easier for polluters to put more toxic and cancer-causing chemicals in waters such as PFAS, arsenic, and pesticides; and provisions that endanger not only our own health but the health of local, regional, and State economies. These were all defeated on party-line votes, unfortunately.
Honestly, I do look forward to the Transportation and Infrastructure Committee returning to its bipartisan work and creating effective legislation that will upgrade our infrastructure, that will build our economy and create jobs, all while protecting our waters.
Mr. Chair, unfortunately, the outcome of this bill, if enacted, will be increasing pollution and contamination of our waters. I oppose this bill, and I urge my colleagues to do the same.
Text printed in the Record (1,046 characters)
SEC. __. PROHIBITION ON DEPRIVING RURAL, TRIBAL, AND
ECONOMICALLY-DISADVANTAGED COMMUNITIES OF CLEAN
WATER.
The Administrator of the Environmental Protection Agency, the Secretary of the Army, acting through the Chief of Engineers, and each State may not implement any amendment made by this Act that will result in--
(1) increasing the volume, toxicity, or concentration of pollutants in a waterbody that has been designated by a State or an Indian Tribe for--
(A) use supplying, or supporting the supply of, public water; or
(B) recreation;
(2) limiting the ability of the Administrator or a State to develop and implement a water quality standard, pretreatment requirement, or effluent limitation, solely on the basis of cost of compliance to the discharger; or
(3) increasing the rates charged for wastewater treatment services (including in rural, Tribal, or economically disadvantaged communities) as a result of transferring the cost for removing any pollutants, or treating such waterbody, to protect the public health or welfare.
Rashida Tlaib (D-MI)12:00 p.m.
Mr. Chairman, we know that the dirty water bill reduces significant oversight for the Clean Water Act, and it is really important to know that polluters are pushing to weaken this--not residents, not families, and not communities that are directly impacted.
This is about discharging toxic chemicals into our water bodies. I want Members to understand that last year, Congress rejected--again, Congress rejected last year many of the changes being proposed now in the PERMIT Act because it had damaging impacts to the health of families, the economy, and our environment.
Mr. Chairman, it is not just this bill. This week, Republicans are voting now on five dirty energy bills that attack communities I represent. These bills boost dirty energy power plants even as energy companies are transitioning toward cleaner energy.
Dirty energy plants have historically been located in communities that look like mine, in rural communities and minority communities. In Michigan, we already know that certain communities are facing a disproportionate burden from electricity generation.
Just ask the residents of southwest Detroit and the Downriver region in Michigan. They have felt the harm and seen the harm, and they lived the experience of being next to DTE's oil-fired power plant that made them sick.
Mr. Chairman, it is immoral, and Congress must fix it. Yet, many of the pro-polluting Republicans in this Chamber want to talk about making electricity with "reliable generation facilities," when they really are talking about more expensive dirty energy.
There is nothing "reliable" about air pollution giving our children asthma. Children not only have the right to be able to not go hungry, but they have a right to breathe clean air. The only thing folks can rely on right now with these plants is getting sicker.
I proposed two amendments this week, Mr. Chair, to protect our communities, but they were rejected. They would have made sure that we have full information and transparency on the disparate impacts and cumulative impacts on minority, rural, disadvantaged, and Tribal communities and would have added safeguards, safeguards that would have been able to define what real reliable generation facilities are.
Again, they were not interested. Why? It is because we know that clean water and clean air is never a priority. It is always going to be about profits for corporate, polluting donors. If you want reliable generation facilities, make them clean so they are not actively poisoning our neighbors, destroying our communities, and making them less attractive places to live, work, and invest.
I promise, if you go to your community and ask them about this dirty water permit bill that you guys are pushing for, as well as what was passed with the energy bills, overwhelmingly, across party lines, they will tell you to protect our land, our soil, our water, our environment, and our health.
Text printed in the Record (5,822 characters)
Adirondack Council, Alabama Rivers Alliance, Alliance for Appalachia, Alliance for Sustainability, American Fisheries Society, American Fly Fishing Trade Association, American Rivers Action Fund, American Sustainable Business Network, American Whitewater, Appalachian Citizens' Law Center, Arkansas Wildlife Federation, Backcountry Hunters & Anglers, Bayou City Waterkeeper, Beaverdam Creek Watershed Watch Group, Black Warrior Riverkeeper, Black-Sampit Riverkeeper, Buffalo Niagara Waterkeeper, Businesses for Bristol Bay, California Environmental Voters, Californians for Weston Wilderness.
CalWild, Center for Biological Diversity, Chesapeake Bay Foundation, Chesapeake Legal Alliance, Children's Environmental Health Network, Chispa Arizona, Citizens Action Coalition of IN, Citizens Campaign for the Environment, Citizens to Conserve and Restore Indian Creek, City of Goshen, Indiana, Stormwater Department, Clean Water Action, Clean Water Action Council of Northeast Wisconsin, Climate Justice Alliance, Commercial Fisherman for Bristol Bay, Committee on the Middle Fork Vermilion River, Community Water Center, Connecticut League of Conselvation Voters, Connecticut River Conservancy, Conservation Alabama, Conservation Coalition of Oklahoma.
Conservation Council for Hawai'i, Conservation Federation of Missouri, Conservation Law Center, Conservation Northwest, Conservation Society of San Antonio, Conservation Voters New Mexico, Conservation Voters of PA, Crawford Stewardship Project, Delaware Nature Society, Delaware-Otsego Audubon Society, Earth Charter Indiana, Earthjustice Action, Eastern PA Coalition for Abandoned Mine, Reclamation (EPCAMR), Elkhart River Restoration Association, Endangered Habitats League, Environmental Advocates NY, Environmental Defenders of McHenly County, Environmental Defense Fund, Environmental Integrity Project, Environmental Law & Policy Center, Environmental League of Massachusetts, Environmental Working Group, Eureka Recycling, Flow Water Advocates, Food & Water Watch, Freshwater Future, Friends of Bell Smith Springs, Friends of the Boundary Water Wilderness, Friends of the Fox River, Friends of the Mississippi River, Friends of the Rouge, Georgia Wildlife Federation, Great Lakes Business Network, Great Lakes Odyssey Radio Hour, Greater Edwards Aquifer Alliance, GreenLatinos, Hays Residents For Land and Water Protection, Hip Hop Caucus, Holy Spirit Missionary Sisters, USA-JPIC, Hoosier Environmental Council, Huron Pines, Huron River Watershed Council, Hydropower Reform Coalition (HRC), Illinois Division lzaak Walton League of America, Illinois Environmental Council, Indiana Conservation Voters, Indiana Forest Alliance, Indiana Retired Teachers Association, Indiana Sportsmens Roundtable, Indiana Wildlife Federation.
Iowa Environmental Council, Iowa Wildlife Federation, lzaak Walton League of America, lzaak Walton League of America-National Great, Lakes Committee, Izaak Walton League, Ohio Division, Just Transition Northwest Indiana, Kentucky Resources Council, Kentucky Waterways Alliance, Labadie Environmental Organization (LEO), Lake Erie Advocates, League of Conservation Voters, Llano River Watershed Alliance, Maine Conservation Voters, Market Square Presbyterian Church, Harrisburg, PA, Maryland Nonprofits, Massachusetts Rivers Alliance, Michigan City Sustainability Commission, Michigan Climate Action Network, Michigan League of Conservation Voters, Mill Creek Alliance, Milwaukee Riverkeeper, Milwaukee Water Commons, Minnesota Center for Environmental Advocacy, Minnesota Division Izaak Walton League of America.
Minnesota Environmental Partnership, Minnesota Trout Unlimited, Montana Wildlife Federation, MS Communities United for Prosperity (MCUP), N.C. Coastal Federation, National Audubon Society, National Parks Conservation Association, National Wildlife Federation, Native American Rights Fund, Natural Resources Council of Maine, Natural Resources Defense Council, NC League of Conservation Voters, Nebraska Wildlife Federation, Nevada Conservation League, Nevada Wildlife Federation, New Hampshire Audubon, New Jersey League of Conservation Voters, New Mexico Wildlife Federation, New York Department of Environmental Conservation, Next 100 Coalition, North Carolina Wildlife Federation, North Dakota Wildlife Federation, Northeastern Minnesotans for Wilderness, NY/NJ Baykeeper, Ohio Environmental Council, Ohio River Foundation, One Mississippi, Oregon Department of Environmental Quality, Oregon League of Conservation Voters, Parable of the Sower Healing Center (Intentional Community Cooperative), Park Watershed, Partners for Clean Streams, Planning and Conservation League, Prairie Rivers Network, Restore America's Estuaries, River Alliance of Wisconsin, Riverkeeper, SalmonState, Save Our Water, Save the Dunes, Sierra Club, Socially Responsible Agriculture Project, Sociedad Ornitologica Puertorriquena, Inc, South Dakota Wildlife Federation, Southeast Alaska Conservation Council, Southern Environmental Law Center, Texas Conservation Alliance, The Alaska Center, The Alliance for
Appalachia, The Land Conservancy of McHenry County,The Michigan Forest Association, Town of Clermont, Trout Unlimited, United Tribes of Bristol Bay, Universal Access to Clean Water for Tribal Communities, Upper Sugar River Watershed Association, Upstream Pgh, Valley Sewardship Network, Vermnont Natural Resources Council, Virginia Conservation Network, Virginia League of Conservation Voters, Washington Conselvation Action, Washington State Department of Ecology, Waterkeeper Alliance, Waterkeepers Chesapeake, WaterLegacy, WE ACT for Environmental Justice, West Virginia Rivers Coalition, Wetlands Watch, Wild Salmon Center, Wildlife for All, Winyah Rivers Alliance, Wisconsin Conservation Voters, Wyoming Wilderness Association.
The text of the bill, as amended, is as follows:
Text printed in the Record (7,494 characters)
Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled,
SECTION 1. SHORT TITLE; TABLE OF CONTENTS.
(a) Short Title.--This Act may be cited as the "Promoting
Efficient Review for Modern Infrastructure Today Act" or the
"PERMIT Act".
(b) Table of Contents.--The table of contents for this Act
is as follows: Sec. 1. Short title; table of contents. Sec. 2. Water quality standards attainability. Sec. 3. Water quality criteria development and transparency. Sec. 4. Water quality technology availability. Sec. 5. Improving water quality certifications and American energy
infrastructure. Sec. 6. Clarifying Federal general permits. Sec. 7. NPDES permit terms. Sec. 8. Confidence in clean water permits. Sec. 9. Forest protection and wildland firefighter safety. Sec. 10. Agricultural stormwater discharge. Sec. 11. Reducing regulatory burdens. Sec. 12. Reducing permitting uncertainty. Sec. 13. Nationwide permitting improvement. Sec. 14. Deadline for request for submission of additional information
for permit programs for dredged or fill material. Sec. 15. Judicial review timeline clarity. Sec. 16. Restoring federalism in clean water permitting. Sec. 17. Jurisdictional determination backlog reduction. Sec. 18. Definition of navigable waters. Sec. 19. Applicability of Spill Prevention, Control, and Countermeasure
rule. Sec. 20. Coordination with Federal Permitting Improvement Steering
Council. Sec. 21. Sense of Congress on Chesapeake Bay Watershed Agreement.
SEC. 2. WATER QUALITY STANDARDS ATTAINABILITY.
(a) State Water Quality Standards.--Section 303(c) (33 U.S.C. 1313(c)) of the Federal Water Pollution Control Act is amended--
(1) in paragraph (1)--
(A) by striking "The Governor of a State" and inserting "(A) The Governor of a State"; and
(B) by striking "Results of such review shall be made available to the Administrator." and inserting the following:
"(B) Reviews under this paragraph shall include review, for purposes of ensuring that combined sewer overflow controls are cost effective, of any water quality standard applicable to a body of water into which, pursuant to a permit, order, or decree issued pursuant to this Act, a municipal combined storm and sanitary sewer discharges.
"(C) Results of each review under this paragraph shall be made available to the Administrator."; and
(2) in paragraph (2)(A)--
(A) by inserting "(i)" before "their use and value for public water supplies";
(B) by striking ", and also taking into consideration" and inserting "; (ii)"; and
(C) by inserting before the period at the end the following: "; and (iii) the cost and commercial availability in the United States of treatment technologies (including whether the technologies have been demonstrated at an applicable scale) that may be required to be applied to point sources in order to result in compliance with such standards".
(b) State Water Quality Criteria.--Section 304(a) of the Federal Water Pollution Control Act (33 U.S.C. 1314(a)) is amended by adding at the end the following new paragraph:
"(10) Consideration of treatment technologies.--In developing or revising water quality criteria under this subsection, the Administrator shall take into consideration the cost and commercial availability in the United States of treatment technologies (including whether the technologies have been demonstrated at an applicable scale) that may be required to be applied to point sources in order to result in compliance with water quality standards adopted or promulgated under section 303.".
SEC. 3. WATER QUALITY CRITERIA DEVELOPMENT AND TRANSPARENCY.
(a) Information and Guidelines.--Section 304(a) of the Federal Water Pollution Control Act (33 U.S.C. 1314(a)) is further amended by adding at the end the following:
"(11) Administrative procedure.--After the date of enactment of this paragraph, the Administrator shall issue any new or revised water quality criteria under paragraph (1) or (9) by rule.".
(b) Administrative Procedure and Judicial Review.--Section 509(b)(1) of the Federal Water Pollution Control Act (33 U.S.C. 1369(b)(1)) is amended--
(1) by striking "section 402, and" and inserting "section 402,"; and
(2) by inserting "and (H) in issuing any criteria for water quality pursuant to section 304(a)(11)," after "strategy under section 304(l),".
SEC. 4. WATER QUALITY TECHNOLOGY AVAILABILITY.
Section 304(b) of the Federal Water Pollution Control Act (33 U.S.C. 1314(b)) is amended--
(1) in paragraph (1)(B), by inserting "the commercial availability in the United States of the technology (including whether the technology has been demonstrated at an applicable scale)," before "and such other factors";
(2) in paragraph (2)(B), by inserting "the commercial availability in the United States of the technology (including whether the technology has been demonstrated at an applicable scale)," before "and such other factors"; and
(3) in paragraph (4)(B), by inserting "the commercial availability in the United States of the technology (including whether the technology has been demonstrated at an applicable scale)," before "and such other factors".
SEC. 5. IMPROVING WATER QUALITY CERTIFICATIONS AND AMERICAN
ENERGY INFRASTRUCTURE.
Section 401 of the Federal Water Pollution Control Act (33 U.S.C. 1341) is amended--
(1) in subsection (a)--
(A) in paragraph (1)--
(i) in the first sentence, by striking "may result" and inserting "may directly result";
(ii) in the second sentence, by striking "activity" and inserting "discharge";
(iii) in the third sentence, by striking "applications" each place it appears and inserting "requests";
(iv) in the fifth sentence, by striking "act on a request for certification, within a reasonable period of time (which shall not exceed one year) after receipt of such request, the certification requirements of this subsection" and inserting "grant the request for certification with or without conditions, deny the request for certification, or waive the requirement for certification under this subsection with respect to such Federal application, within a reasonable period of time to be determined by the licensing or permitting agency (which shall not exceed one year) after receipt of such request, the requirement for certification under this subsection";
(v) in the sixth sentence, by striking "waived as provided in the preceding sentence" and inserting "waived under this paragraph"; and
(vi) by inserting after the fourth sentence the following: "Not later than 30 days after the date of enactment of the PERMIT Act, each State and interstate agency that has authority to give such a certification, and the Administrator, shall publish requirements for certification to demonstrate to such State, such interstate agency, or the Administrator, as the case may be, compliance with the applicable provisions of sections 301, 302, 303, 306, and 307. A decision to grant or deny a request for certification shall be based only on compliance with the applicable provisions of sections 301, 302, 303, 306, and 307, and the grounds for the decision shall be set forth in writing and provided to the applicant. Not later than 90 days after receipt of a request for certification, the State, interstate agency, or Administrator, as the case may be, shall identify in writing all specific additional materials or information necessary for the request for certification to be complete, as described in subsection (g).
Text printed in the Record (11,907 characters)
The State, interstate agency, or the Administrator, as the case may be, may grant a request for certification with or without conditions, deny a request for certification, or waive the requirement for certification under this subsection with respect to such Federal application.";
(B) in paragraph (2)--
(i) in the second sentence, by striking "notice of application for such Federal license or permit" and inserting "receipt of a notice under the preceding sentence";
(ii) in the third sentence--
(I) by striking "any water quality requirement in such State" and inserting "any water quality standard in effect for the State under section 303"; and
(II) by inserting before the period "at a time that is agreed to by such State and the applicant";
(iii) in the fifth sentence, by striking "insure compliance with applicable water quality requirements." and inserting "ensure compliance with the applicable provisions of sections 301, 302, 303, 306, and 307.";
(iv) in the final sentence, by striking "insure" and inserting "ensure";
(v) by striking the first sentence and inserting "On receipt of a request for certification, the certifying State or interstate agency, as applicable, shall immediately notify the Administrator of the request."; and
(vi) by inserting after the second sentence the following: "If the Administrator determines under the preceding sentence that such a discharge will not affect the waters of any other State, no such notification is required.";
(C) in paragraph (3)--
(i) in the first sentence, by striking "there will be compliance" and inserting "any such discharge will comply"; and
(ii) in the second sentence, by striking "section" and inserting "any applicable provision of section";
(D) in paragraph (4)--
(i) in the first sentence--
(I) by inserting "directly" before "result in any discharge"; and
(II) by striking "applicable effluent limitations or other limitations or other applicable water quality requirements will not be violated" and inserting "no applicable provision of section 301, 302, 303, 306, or 307 will be violated";
(ii) in the second sentence, by striking "will violate applicable effluent limitations or other limitations or other water quality requirements" and inserting "will directly result in a discharge that violates an applicable provision of section 301, 302, 303, 306, or 307,"; and
(iii) in the third sentence, by striking "such facility or activity will not violate the applicable provisions" and inserting "operation of such facility or activity will not directly result in a discharge that violates any applicable provision"; and
(E) in paragraph (5), by striking "the applicable provisions" and inserting "any applicable provision";
(2) in subsection (b), by striking "Nothing in this section" and inserting "Except as provided in subsection (e), nothing in this section";
(3) in subsection (d), by striking "applicant for a Federal license or permit will comply with any applicable effluent limitations and other limitations, under section 301 or 302 of this Act, standard of performance under section 306 of this Act, or prohibition, effluent standard, or pretreatment standard under section 307 of this Act, and with any other appropriate requirement of State law set forth in such certification, and shall become a condition on any Federal license or permit subject to the provisions of this section" and inserting "discharge subject to this section will comply with the applicable provisions of sections 301, 302, 303, 306, and 307, and any such limitations or requirements shall be imposed by the licensing or permitting agency as a condition on any Federal license or permit subject to the provisions of this section"; and
(4) by adding at the end the following:
"(e) Notwithstanding section 505, any condition imposed on a Federal license or permit by a licensing or permitting agency under this section may be enforced only by such licensing or permitting agency.
"(f) For purposes of this section, the applicable provisions of sections 301, 302, 303, 306, and 307 are any applicable effluent limitations and other limitations under section 301 or 302, any water quality standard in effect for a State under section 303, any standard of performance under section 306, and any prohibition, effluent standard, or pretreatment standard under section 307.
"(g) A request for certification under this section shall be made in writing to the State, interstate agency, or Administrator, as the case may be. A complete request for certification shall consist of the following:
"(1) Identification of each applicant for the Federal license or permit with respect to which the certification is requested.
"(2) A statement that information included in the request for certification is truthful, accurate, and complete, to the best knowledge of each such applicant.
"(3) In the case of a request for certification with respect to an individual permit or license--
"(A) identification of the Federal license or permit that is the subject of the application with respect to which the certification is requested;
"(B) identification of any activity the conduct of which is subject to such Federal license or permit;
"(C) identification of the location and nature of any discharge that may directly result from such activity, and the location of the receiving waters;
"(D) a description of means that may be used to monitor, control, or manage any such discharge; and
"(E) a list of all other Federal, interstate, Tribal, State, or local agency authorizations required for the conduct of such activity, and any approval or denial of such an authorization already received.
"(4) In the case of a request for certification with respect to the issuance of a general license or general permit--
"(A) identification of the proposed categories of activities to be covered by the general license or general permit for which certification is requested;
"(B) a description of the proposed general license or general permit, which may include a draft of the proposed general license or permit; and
"(C) an estimate of the number of discharges expected to result from the proposed general license or general permit annually.".
SEC. 6. CLARIFYING FEDERAL GENERAL PERMITS.
Section 402(a) of the Federal Water Pollution Control Act (33 U.S.C. 1342(a)) is amended by adding at the end the following:
"(6) General permits.--
"(A) Permits authorized.--The Administrator may issue general permits under this section on a State, regional, or nationwide basis, or for a delineated area, for discharges associated with any category of activities, which discharges are of similar types and from similar sources.
"(B) Permit expiration notification requirement.--If a general permit issued under this section will expire and the Administrator decides not to issue a new general permit for discharges similar to those covered by the expiring general permit, the Administrator shall publish in the Federal Register a notice of such decision at least two years prior to the expiration of the general permit.
"(C) Application of permit terms of an expired permit.--
"(i) In general.--If a general permit issued under this section expires and the Administrator has not published a notice in accordance with subparagraph (B), the Administrator shall, until the date described in clause (ii)--
"(I) continue to apply the terms, conditions, and requirements of the expired general permit to any discharge that was covered by the expired general permit; and
"(II) apply such terms, conditions, and requirements to any discharge that would have been covered by the expired general permit (in accordance with any relevant requirements for such coverage) if the discharge had occurred before such expiration.
"(ii) Date described.--The date described in this clause is the earlier of--
"(I) the date on which the Administrator issues a new general permit for discharges similar to those covered by the expired general permit; or
"(II) the date that is two years after the date on which the Administrator publishes in the Federal Register a notice of a decision not to issue a new general permit for discharges similar to those covered by the expired general permit.".
SEC. 7. NPDES PERMIT TERMS.
Section 402(b)(1)(B) of the Federal Water Pollution Control Act (33 U.S.C. 1342(b)(1)(B)) is amended by striking "five years" and inserting "ten years".
SEC. 8. CONFIDENCE IN CLEAN WATER PERMITS.
(a) Compliance With Permits.--Section 402(k) of the Federal Water Pollution Control Act (33 U.S.C. 1342(k)) is amended--
(1) by striking "(k) Compliance with" and inserting the following:
"(k) Compliance With Permits.--
"(1) In general.--Subject to paragraph (2), compliance with"; and
(2) by adding at the end the following:
"(2) Scope.--For purposes of paragraph (1), compliance with the conditions of a permit issued under this section shall be considered compliance with respect to a discharge of--
"(A) any pollutant for which an effluent limitation is included in the permit; and
"(B) any pollutant for which an effluent limitation is not included in the permit that is--
"(i) specifically identified as controlled or monitored through indicator parameters in the permit, the fact sheet for the permit, or the administrative record relating to the permit;
"(ii) specifically identified during the permit application process as present in discharges to which the permit will apply; or
"(iii) whether or not specifically identified in the permit or during the permit application process--
"(I) present in any waste streams or processes of the point source to which the permit applies, which waste streams or processes are specifically identified during the permit application process; or
"(II) otherwise within the scope of any operations of the point source to which the permit applies, which scope of operations is specifically identified during the permit application process.".
(b) Expression of Water Quality-Based Effluent Limitations.--Section 402 of the Federal Water Pollution Control Act (33 U.S.C. 1342) is amended by adding at the end the following:
"(t) Expression of Water Quality-Based Effluent Limitations.--If the Administrator (or a State, in the case of a permit program approved by the Administrator) determines that a water quality-based limitation on a discharge of a pollutant is necessary to include in a permit under this section in addition to any appropriate technology-based effluent limitations included in such permit, the Administrator (or the State) may include such water quality-based limitation in such permit only in the form of a limitation that--
"(1) specifies the pollutant to which it applies; and
"(2) clearly describes the manner in which compliance with the limitation may be achieved, which shall include--
"(A) a numerical limit on the discharge of such pollutant;
"(B) a narrative description of required actions to be applied to the discharge (including any measures or practices required to be applied); or
"(C) a narrative description of a limitation on the discharge that specifies the level of control to be applied.".
SEC. 9. FOREST PROTECTION AND WILDLAND FIREFIGHTER SAFETY.
Section 402(l)(3)(A) of the Federal Water Pollution Control Act (33 U.S.C. 1342(l)(3)(A)) is amended--
(1) by striking "for a discharge from" and inserting the following: "for--
"(i) a discharge from";
(2) in clause (i) (as so designated), by striking the period at the end and inserting "; or"; and
(3) by adding at the end the following:
"(ii) a discharge resulting from the aerial application of a product used for fire control and suppression purposes that appears on the most current Forest Service Qualified Products List (or any successor list).".
SEC. 10. AGRICULTURAL STORMWATER DISCHARGE.
Section 402(l) of the Federal Water Pollution Control Act (33 U.S.C.
Text printed in the Record (9,532 characters)
1342(l)) is amended by adding at the end the following:
"(4) Agricultural stormwater discharge.--
"(A) In general.--The Administrator shall not require a permit, nor directly or indirectly require any State to require a permit, under this section for discharges of stormwater, including from subsurface drainage, from agricultural land that occur in direct response to a precipitation event.
"(B) Agricultural land defined.--In this paragraph, the term `agricultural land' includes--
"(i) land on which an agricultural input (such as manure and other crop nutrients, crop protection, or seed) is applied;
"(ii) land on which animals (including fish and shellfish), crops (including fruit and nut trees), crop residue, plants, seed, or vegetation are present for purposes of farming or ranching; and
"(iii) land that is--
"(I) immediately adjacent to, and functionally related to, land described in clause (i) or (ii); and
"(II) necessary to support agricultural production, soil conservation, flood control, or water quality.".
SEC. 11. REDUCING REGULATORY BURDENS.
Section 402 of the Federal Water Pollution Control Act (33 U.S.C. 1342) is further amended by adding at the end the following:
"(u) Discharges of Pesticides.--
"(1) No permit requirement.--Except as provided in paragraph (2), a permit shall not be required by the Administrator or a State under this Act for a discharge from a point source into navigable waters of a pesticide authorized for sale, distribution, or use under the Federal Insecticide, Fungicide, and Rodenticide Act, or the residue of such a pesticide, resulting from the application of such pesticide.
"(2) Exceptions.--Paragraph (1) shall not apply to the following discharges of a pesticide or pesticide residue:
"(A) A discharge resulting from the application of a pesticide in violation of a provision of the Federal Insecticide, Fungicide, and Rodenticide Act that is relevant to protecting water quality, if--
"(i) the discharge would not have occurred but for the violation; or
"(ii) the amount of pesticide or pesticide residue in the discharge is greater than would have occurred without the violation.
"(B) Stormwater discharges subject to regulation under subsection (p).
"(C) The following discharges subject to regulation under this section:
"(i) Manufacturing or industrial effluent.
"(ii) Treatment works effluent.
"(iii) Discharges incidental to the normal operation of a vessel, including a discharge resulting from ballasting operations or vessel biofouling prevention.".
SEC. 12. REDUCING PERMITTING UNCERTAINTY.
(a) In General.--Section 404(c) of the Federal Water Pollution Control Act (33 U.S.C. 1344(c)) is amended--
(1) by striking "(c) The Administrator" and inserting the following:
"(c) Specification or Use of Defined Area.--
"(1) In general.--The Administrator";
(2) in paragraph (1), as so designated, by inserting "during the period described in paragraph (2) and" before "after notice and opportunity for public hearings"; and
(3) by adding at the end the following:
"(2) Period of prohibition.--The period during which the Administrator may prohibit the specification (including the withdrawal of specification) of any defined area as a disposal site, or deny or restrict the use of any defined area for specification (including the withdrawal of specification) as a disposal site, under paragraph (1) shall--
"(A) begin on the date on which an applicant submits all the information required to complete an application for a permit under this section; and
"(B) end on the date on which the Secretary issues the permit.".
(b) Applicability.--The amendments made by subsection (a) shall apply to a permit application submitted under section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344) after the date of enactment of this Act.
SEC. 13. NATIONWIDE PERMITTING IMPROVEMENT.
(a) In General.--Section 404(e) of the Federal Water Pollution Control Act (33 U.S.C. 1344) is amended--
(1) by striking "(e)(1) In carrying" and inserting the following:
"(e) General Permits.--
"(1) Permits authorized.--In carrying";
(2) in paragraph (2)--
(A) by striking "(2) No general" and inserting the following:
"(2) Term.--No general"; and
(B) by striking "five years" and inserting "ten years"; and
(3) by adding at the end the following:
"(3) Considerations.--In determining the environmental effects of an activity under paragraph (1) or (2), the Secretary--
"(A) shall consider only the effects of any discharge of dredged or fill material resulting from such activity;
"(B) shall consider any effects of a discharge of dredged or fill material into less than 3 acres of navigable waters to be a minimal adverse environmental effect; and
"(C) may consider any effects of a discharge of dredged or fill material into 3 acres or more of navigable waters to be a minimal adverse environmental effect.
"(4) Nationwide permits for linear projects.--
"(A) In general.--Notwithstanding any other provision of this section, the Secretary shall maintain general permits on a nationwide basis for--
"(i) linear infrastructure projects that result in a discharge of dredged or fill material into less than 3 acres of navigable waters for each single and complete project; and
"(ii) linear pipeline projects that do not result in the loss of navigable waters in an amount that is greater than 0.5 acres for each single and complete project.
"(B) Definitions.--In this paragraph:
"(i) Linear infrastructure project.--The term `linear infrastructure project' means a project to carry out any activity required for the construction, expansion, maintenance, modification, or removal of infrastructure and associated facilities for the transmission from a point of origin to a terminal point of communications or electricity, or for the transportation from a point of origin to a terminal point of people, water, or wastewater.
"(ii) Linear pipeline project.--The term `linear pipeline project' means a project to carry out any activity required for the construction, expansion, maintenance, modification, or removal of infrastructure and associated facilities for the transportation from a point of origin to a terminal point of carbon dioxide, fuel, or hydrocarbons, in the form of a liquid, liquescent, gaseous, or slurry substance or supercritical fluid, including oil and gas pipeline facilities.
"(iii) Single and complete project.--The term `single and complete project' has the meaning given that term in section 330.2 of title 33,
Code of Federal Regulations (as in effect on the date of enactment of this paragraph).
"(5) Reissuance of nationwide permits.--In determining whether to reissue a general permit issued under this subsection on a nationwide basis--
"(A) no consultation with an applicable State pursuant to section 6(a) of the Endangered Species Act of 1973 (16 U.S.C. 1535(a)) is required;
"(B) no consultation with a Federal agency pursuant to section 7(a)(2) of such Act (16 U.S.C. 1536(a)(2)) is required; and
"(C) the requirements of section 102(2)(C) of the National Environmental Policy Act of 1969 (42 U.S.C. 4332(2)(C)) shall be satisfied by preparing an environmental assessment with respect to such general permit.".
(b) Regulatory Revisions Required.--The Secretary of the Army, acting through the Chief of Engineers, shall expeditiously revise the regulations applicable to carrying out section 404(e) of the Federal Water Pollution Control Act (33 U.S.C. 1344) in order to streamline the processes for issuing general permits under such section to promote efficient and consistent implementation of such section.
(c) Administration of Nationwide Permit Program.--In carrying out section 404(e) of the Federal Water Pollution Control Act (33 U.S.C. 1344), including in revising regulations under subsection (b) of this section, the Secretary of the Army, acting through the Chief of Engineers, may not finalize or implement any modification to--
(1) general condition 15 (relating to single and complete projects), as included in the final rule titled "Reissuance and Modification of Nationwide Permits" and published on January 13, 2021, by the Department of the Army, Corps of Engineers (86 Fed. Reg. 2868);
(2) the definition of the term "single and complete linear project", as included in such final rule (86 Fed. Reg. 2877); or
(3) the definition of the term "single and complete project", as included in section 330.2 of title 33, Code of Federal Regulations (as in effect on the date of enactment of this Act).
SEC. 14. DEADLINE FOR REQUEST FOR SUBMISSION OF ADDITIONAL
INFORMATION FOR PERMIT PROGRAMS FOR DREDGED OR
FILL MATERIAL.
Section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344) is amended--
(1) in subsection (g)--
(A) by redesignating paragraph (3) as paragraph (4); and
(B) by inserting after paragraph (2) the following:
"(3) If the Administrator determines that additional information is necessary for the description of a program submitted by a State to be full and complete under paragraph (1), the Administrator shall, not later than 45 days after the date of the receipt of the program and statement submitted by the State under such paragraph, submit to the State a written request for all such information."; and
(2) in subsection (h)(1), by striking "paragraph (1) of this subsection" and inserting "subsection (g)(1)".
SEC. 15. JUDICIAL REVIEW TIMELINE CLARITY.
Section 404 of the Federal Water Pollution Control Act (33 U.S.C.
Text printed in the Record (9,437 characters)
1344) is amended--
(1) by redesignating subsection (t) as subsection (u);
(2) in subsection (u), as so redesignated, by striking "Nothing in the section" and inserting "Savings Provision.--Nothing in this section"; and
(3) by inserting after subsection (s) the following:
"(t) Judicial Review.--
"(1) Statute of limitations.--Notwithstanding any applicable provision of law relating to statutes of limitations--
"(A) an action seeking judicial review of the approval by the Administrator of a State permit program pursuant to this section shall be filed not later than the date that is 60 days after the date on which the approval was issued;
"(B) an action seeking judicial review of an individual permit or general permit issued under this section shall be filed not later than the date that is 60 days after the date on which the permit was issued; and
"(C) an action seeking judicial review of a verification that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section shall be filed not later than the date that is 60 days after the date on which such verification was issued.
"(2) Limitation on commencement of certain actions.--Notwithstanding any other provision of law, no action described in subparagraph (A) or (B) of paragraph (1) may be commenced unless the action--
"(A) is filed by a party that submitted a comment--
"(i) during the public comment period for the administrative proceedings related to the action; and
"(ii) which was sufficiently detailed to put the Administrator, the Secretary, or the State, as applicable, on notice of the issue upon which the party seeks judicial review; and
"(B) is related to such comment.
"(3) Remedies.--
"(A) Actions relating to permit programs.--If a court determines that the Administrator did not comply with the requirements of this section in issuing an approval of a State permit program pursuant to this section--
"(i) the court shall remand the matter to the Administrator for further proceedings consistent with the determination of the court; and
"(ii) the court may not vacate, revoke, enjoin, or otherwise limit the authority of the State to issue permits under such State permit program.
"(B) Actions relating to permits.--If a court determines that the Secretary or the State, as applicable, did not comply with the requirements of this section in issuing an individual or general permit under this section, or in verifying that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section, as applicable--
"(i) the court shall remand the matter to the Secretary or the State, as applicable, for further proceedings consistent with the determination of the court;
"(ii) with respect to a determination regarding the issuance of an individual or general permit under this section, the court may not vacate, revoke, enjoin, or otherwise limit the permit, unless the court finds that activities authorized under the permit would present an imminent and substantial danger to human health or the environment for which there is no other equitable remedy available under the law; and
"(iii) with respect to a determination regarding a verification that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section, the court may not enjoin or otherwise limit the discharge unless the court finds that the activity would present an imminent and substantial danger to human health or the environment for which there is no other equitable remedy available under the law.
"(4) Timeline to act on court order.--If a court remands a matter under paragraph (3), the court shall set and enforce a reasonable schedule and deadline, which may not exceed 180 days from the date on which the court remands such matter, except as otherwise required by law, for the Administrator, the Secretary, or the State, as applicable, to take such actions as the court may order.".
SEC. 16. RESTORING FEDERALISM IN CLEAN WATER PERMITTING.
Not later than 180 days after the date of enactment of this Act, the Administrator of the Environmental Protection Agency shall complete a review of the regulations applicable to the approval of State permit programs under section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344) in order to identify revisions to such regulations necessary to streamline the approval process, reduce administrative burdens, and encourage additional States to administer a permit program under such section, and the Administrator shall implement any such revisions as appropriate.
SEC. 17. JURISDICTIONAL DETERMINATION BACKLOG REDUCTION.
Not later than 60 days after the date of enactment of this Act, the Secretary of the Army, acting through the Chief of Engineers, shall expedite such procedures and reallocate or augment such personnel and resources of the Corps of Engineers as the Secretary determines necessary to eliminate any backlog existing as of June 5, 2025, of--
(1) applications for permits under section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344); or
(2) requests for jurisdictional determinations or wetlands delineations under the jurisdiction of the Secretary.
SEC. 18. DEFINITION OF NAVIGABLE WATERS.
Section 502(7) of the Federal Water Pollution Control Act (33 U.S.C. 1362(7)) is amended--
(1) by striking "(7) The term" and inserting the following:
"(7) Navigable waters.--
"(A) In general.--The term"; and
(2) by adding at the end the following:
"(B) Exclusions.--The term `navigable waters' does not include the following:
"(i) Any component of a waste treatment system, including any lagoon or treatment pond (such as a settling or cooling pond), designed to actively or passively--
"(I) convey or retain wastewater; or
"(II) concentrate, settle, reduce, or remove pollutants from wastewater.
"(ii) Ephemeral features that flow only in direct response to precipitation.
"(iii) Any area that--
"(I) prior to December 23, 1985, was drained or otherwise manipulated for the purpose, or having the effect, of making production of an agricultural product possible, as determined by the Administrator and the Secretary of the Army, acting through the Chief of Engineers, which determinations shall be consistent with any designations of prior converted cropland made by the Secretary of Agriculture; and
"(II) as determined by the Administrator--
"(aa) at least once in the immediately preceding five years has been used for, or in support of, agricultural purposes, including grazing, haying, idling land for conservation use (such as habitat management, pollinator and wildlife management, water storage and supply management, and flood management), irrigation tailwater storage, farm-raised fish production, cranberry production, nutrient retention, and idling land for soil recovery after natural disasters such as hurricanes and drought; and
"(bb) has not reverted to wetlands (as defined in section 120.2 of title 40, Code of Federal Regulations, as in effect on the date of enactment of this clause).
"(iv) Groundwater.
"(v) Any other features determined to be excluded by the Administrator and the Secretary of the Army, acting through the Chief of Engineers.".
SEC. 19. APPLICABILITY OF SPILL PREVENTION, CONTROL, AND
COUNTERMEASURE RULE.
Section 1049 of the Water Resources Reform and Development Act of 2014 (33 U.S.C. 1361 note) is amended--
(1) in subsection (b)--
(A) in paragraph (1)(B), by striking "20,000" and inserting "42,000";
(B) by amending paragraph (2)(A) to read as follows:
"(A) an aggregate aboveground storage capacity greater than 10,000 gallons but less than 42,000 gallons; and";
(C) in paragraph (3)--
(i) by amending subparagraph (A) to read as follows:
"(A) with an aggregate aboveground storage capacity of less than or equal to 10,000 gallons; and"; and
(ii) in subparagraph (B), by striking "; and" and inserting a period; and
(D) by striking paragraph (4);
(2) in subsection (c)(2)(A)--
(A) in clause (i), by striking "1,000" and inserting "1,320"; and
(B) in clause (ii), by striking "2,500" and inserting "3,000"; and
(3) by striking subsection (d).
SEC. 20. COORDINATION WITH FEDERAL PERMITTING IMPROVEMENT
STEERING COUNCIL.
With respect to any covered project (as defined under section 41001 of the FAST Act (42 U.S.C. 4370m)) for which a certification or permit from a State under section 401, 402, or 404 of the Federal Water Pollution Control Act is required, the State is encouraged to choose to participate, to the maximum extent practicable, in the environmental review and authorization process under section 41003(c) of the FAST Act (42 U.S.C. 4370m-2(c)), pursuant to paragraph (3)(A) of such section.
SEC. 21. SENSE OF CONGRESS ON CHESAPEAKE BAY WATERSHED
AGREEMENT.
It is the sense of Congress that the Chesapeake Bay Watershed Agreement is a voluntary, cooperative agreement between the Federal Government, the State of Delaware, the District of Columbia, the State of Maryland, the Commonwealth of Pennsylvania, the State of New York, the Commonwealth of Virginia, and the State of West Virginia. As such, the Federal Government should take a collaborative and cooperative approach to the parties with regard to their compliance with the Chesapeake Bay Total Maximum Daily Load outlined in such agreement.
The text of the amendment is as follows:
Text printed in the Record (3,810 characters)
Insert after section 15 the following:
SEC. __. MAINTAINING COOPERATIVE PERMITTING.
(a) Withdrawal of Approval Without Congressional Authorization Prohibited.--The permit programs described in subsection (b) are ratified, approved, and of full force and effect, and the Administrator of the Environmental Protection Agency (referred to in this section as the "Administrator") may not withdraw the approval of those permit programs, including through the process described in section 404(i) of the Federal Water Pollution Control Act (33 U.S.C. 1344(i)), unless the withdrawal is expressly authorized by an Act of Congress enacted after the date of enactment of this Act.
(b) Permit Programs Described.--The permit programs referred to in subsection (a) are the following State permit programs for the discharge of dredged or fill material approved under section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344):
(1) The program of the State of Michigan, approved in the notice of the Environmental Protection Agency entitled "Michigan Department of Natural Resources Section 404 Permit Program Approval" (49 Fed. Reg. 38947 (October 2, 1984)) and as described in section 233.70 of title 40, Code of Federal Regulations (including any updates to the program described in a successor Federal Register notice).
(2) The program of the State of New Jersey, approved in the final rule and notice of the Environmental Protection Agency entitled "New Jersey Department of Environmental Protection and Energy Section 404 Permit Program Approval" (59 Fed. Reg. 9933 (March 2, 1994)) and as described in section 233.71 of title 40, Code of Federal Regulations (including any updates to the program described in a successor Federal Register notice).
(3) The program of the State of Florida, as described in the notice of the Environmental Protection Agency entitled "EPA's Approval of Florida's Clean Water Act Section 404 Assumption Request" (85 Fed. Reg. 83553 (December 22, 2020)) (including any updates to the program described in a successor Federal Register notice), including the Programmatic Biological Opinion with Incidental Take Statement associated with the program.
(c) Program Transition Period.--During the 90-day period beginning on the date of enactment of this Act, the Secretary of the Army, acting through the Chief of Engineers (referred to in this section as the "Secretary"), and the State of Florida may both issue permits authorized under the program described in subsection (b)(3) for the discharge of dredged or fill material into navigable waters (as described in subsection 404(g)(1) of the Federal Water Pollution Control Act (33 U.S.C. 1344(g)(1))) within the jurisdiction of the State of Florida.
(d) Approval of Comparable State Programs.--
(1) In general.--If the Administrator determines that a State program submitted under subsection (g)(1) of section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344) is comparable to a State program described in any of paragraphs (1) through (3) of subsection (b) of this section, the Administrator shall make the determination described in subsection (h)(2)(A) of such section 404 with respect to that program.
(2) Notification.--On making the determination required under paragraph (1), the Administrator shall notify the Secretary and the applicable State of that determination.
(3) Suspension.--On notification from the Administrator under paragraph (2) and from a State that the State has begun to administer a program approved pursuant to paragraph (1), the Secretary shall suspend the issuance of permits under subsections (a) and (e) of section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344) for activities with respect to which a permit may be issued by the State under that program.
Text printed in the Record (6,811 characters)
Tallahassee, FL, August 7, 2025. Hon. Aaron Bean, House of Representatives, Washington, DC.
Dear Representative Bean: On behalf of Florida's environment and regulated communities, I would like to voice my support for the Maintaining Cooperative Permitting Act of 2025 (H.R. 2030/S. 1014).
The Act is necessary to set right last year's ruling from a federal district court in Washington, D.C., which vacated the Environmental Protection Agency (EPA)'s approval of Florida's Clean Water Act Section 404 Permitting Program. The Act will also provide a clear and workable path for other states to assume administration of this important program.
The D.C. court's decision, which is contrary to the position of the Trump and Biden Administrations as it relates to Florida's program, has shifted permitting authority back to the federal government, creating enormous disruptions to Florida's efforts to protect wetlands and water resources and is now blocking Florida's ability to issue necessary permits for development projects across the State.
State "assumption" of the Section 404 program is an important part of the Clean Water Act's cooperative federalism structure. Assumption can streamline permitting processes, reduce duplication of effort and overall expenditures by state and federal authorities, while providing better protection of a state's environmental resources by those who know their state best.
Beginning almost a decade ago, Florida began work to establish a comprehensive Section 404 permitting program. After receiving approval from EPA in 2020, Florida trained over 300 certified wetlands evaluators and other staff and received and processed thousands of permit applications for Section 404 permits. Florida's program is consistent with federal Clean Water Act requirements and all permit applications are reviewed by both federal and state wildlife agencies to ensure full protection of threatened or endangered species and their habitats.
I urge you to support the Maintaining Cooperative Permitting Act of 2025 to ensure Florida's Clean Water Act 404 permitting program is rightfully restored to the state.
Sincerely, Alexis A. Lambert.
____
Washington, DC, December 10, 2025.
Hon. Mike Johnson,
Speaker, House of Representatives,
Washington, DC.
Dear Speaker Johnson: On behalf of the more than 140,000
members of the National Association of Home Builders (NAHB),
I am writing to convey our strong support for H.R. 3898, the
PERMIT Act, which will provide necessary clarity and
confidence required under the Clean Water Act (CWA)
permitting process. Because clear and predictable permitting
leads to the creation of attainable housing, NAHB has
designated support for passage of H.R. 3898 as a KEY VOTE.
Regrettably, housing production is not keeping pace with
demand. Among the significant headwinds facing the home
building industry is an unpredictable regulatory landscape
that adds costs and reduces the availability of buildable
lots--making housing more unattainable. This legislation
respects environmental protections and provides pragmatic
solutions to Section 404 and Section 402 of the CWA.
Under Section 404--dredge and fill permitting--home
builders pull some of the highest numbers of Nationwide
Permits (NWPs) issued annually. To assist with planning and
permit backlogs, this legislation extends the duration of a
NWP from 5 to 10 years and right sizes the acreage threshold
for impacts to where the NWP was originally intended.
To better assist states in assuming their own 404
permitting authority, this bill requires the Environmental
Protection Agency to review its regulations and procedures
surrounding the 404 approval process. This will help
streamline and ease administrative burdens states face when
attempting to assume their own permitting program.
A key feature of Section 404 permitting is the Waters of
the United States rule. This bill codifies long-established
exclusions such as ephemeral features, groundwater, and prior
converted cropland that have been included as part of WOTUS
regulations over the years. This will provide important
predictability and consistency for property owners when
determining which water features are jurisdictional.
Under Section 402--the National Pollutant Discharge
Elimination System (NPDES)--this legislation would require
permit writers to tie NPDES permit conditions to what happens
on their site, rather than what happens downstream to impair
receiving waters. This approach allows regulators to explain
the measures that home builders must take to comply with
their NPDES permit, without imposing numeric discharge
limits.
NAHB additionally urges passage of Amendment 27, submitted
by Representative Crawford, pertaining to compensatory
mitigation. Compensatory mitigation has become a significant
cost and barrier for builders: Representative Crawford's
amendment takes meaningful steps towards reducing mitigation
costs through simple, commonsense reforms that maintain
environmental protections while allowing for economic growth.
NAHB also commends Amendment 52, submitted by
Representative Bean, pertaining to state assumption of the
Section 404 program for Florida, Michigan, and New Jersey.
Litigation over state assumption has created significant
uncertainty for CWA permitting nationally, and NAHB urges
Congress to return Section 404 to its original intent,
allowing states to assume the permitting role. This will
provide confidence and clarity for states interested in
Section 404 assumption, and builders within those states.
The home building industry requires certitude in the CWA
permitting process. The PERMIT Act respects environmental
safeguards and makes significant strides in ensuring clarity
in the regulatory process. For these reasons, NAHB
respectfully urges passage on the House floor.
Thank you for considering our views.
Sincerely,
Lake A. Coulson.
Mr. BEAN of Florida. Mr. Chair, I reserve the balance of my time.
Ms. SCHOLTEN. Mr. Chair, I reserve the balance of my time.
Mr. BEAN of Florida. Mr. Chair, this has been a model. This program works. The Reagan administration approved Michigan's program. The Clinton administration approved New Jersey's program. Then Florida's program was approved by the Trump administration and then defended by the Biden administration. This is something we should agree on, bipartisan support to help protect the environment.
Mr. Chair, it is Florida, Michigan, and New Jersey, but here are the States that are in line, that say we
want to protect our own environment, too: Alaska, Arizona, Indiana, Kentucky, Maryland, Minnesota, North Dakota, Oregon, and Virginia. They are all in line to fight for their own State and protect the environment in their own State.
The amendment was agreed to.
The amendment was agreed to.
The text of the amendment is as follows:
Text printed in the Record (61 characters)
Page 37, line 15, strike "five years" and insert "ten years".
The amendment was agreed to.
The text of the amendment is as follows:
Text printed in the Record (1,871 characters)
Add at the end the following:
SEC. __. IDENTIFICATION AND PERMITTING FOR WATER RECHARGE ON
CERTAIN FEDERAL LANDS.
(a) Review and Identification.--Not later than 1 year after the date of enactment of this Act, the Secretary of the Army, acting through the Chief of Engineers, shall review lands under the jurisdiction of the Secretary to identify parcels of such lands that are hydrologically and geologically well-suited for water recharge efforts, including aquifer recharge, surface water infiltration, or managed aquifer recharge projects, taking into consideration factors such as soil permeability, proximity to water sources, and minimal environmental impact.
(b) Streamlined Permitting Process.--The Secretary, in consultation with the Administrator of the Environmental Protection Agency and each relevant State water resource agency, shall--
(1) establish clear and simple permitting processes for water recharge projects on parcels of land identified by the Secretary under subsection (a), including a process to facilitate (to the extent practicable)--
(A) the actions of the Secretary under section 17 applicable to such projects; and
(B) the expedited issuance of a permit under section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344), as amended by this Act, relating to such projects; and
(2) ensure, to the extent practicable, that each process established under paragraph (1) minimizes regulatory burdens, provides for categorical exclusions or streamlined environmental assessments, and promotes collaboration with State and local entities to expand water recharge efforts.
(c) Report to Congress.--Not later than 18 months after the date of enactment of this Act, the Secretary shall submit to Congress a report detailing the parcels identified under subsection (a) and each permitting process established under subsection (b).
The amendment was agreed to.
The Chair understands that amendment No. 5 will not be offered.
The text of the amendment is as follows:
Text printed in the Record (4,758 characters)
Insert after section 16 the following:
SEC. __. REVISION OF FRAMEWORK FOR COMPENSATORY MITIGATION.
(a) Requirement to Revise.--Not later than 180 days after the date of enactment of this Act, the Secretary, in coordination with the Administrator of the Environmental Protection Agency, shall publish in the Federal Register a proposed rule, consistent with section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344), to revise the regulations issued in the final rule of the Department of Defense and the Environmental Protection Agency titled "Compensatory Mitigation for Losses of Aquatic Resources" and published in the Federal Register on April 10, 2008 (73 Fed. Reg. 19594).
(b) Scope of Revisions.--In carrying out subsection (a), the Secretary shall--
(1) incorporate lessons learned since the implementation of the final rule described in subsection (a) and reflect advances in science, restoration practices, and regulatory efficiency;
(2) promote equivalency and flexibility among mitigation options, including mitigation banking, in-lieu fee programs, and permittee-responsible mitigation;
(3) expedite the approval of plans that use mitigation banks, in-lieu fee programs, and permittee-responsible mitigation;
(4) support regional watershed approaches, including by--
(A) encouraging compensatory mitigation credit generation and sales across primary, secondary, and tertiary service areas; and
(B) implementing mitigation requirements, policies, and guidance that are consistent, predictable, and transparent;
(5) ensure timely coordination between Corps of Engineers district offices and Interagency Review Teams;
(6) ensure that, for projects involving temporary impacts to aquatic resources, including mining and other energy or infrastructure projects with approved reclamation plans, the revised regulations--
(A) take into account the temporary nature of such impacts;
(B) recognize activities carried out under an approved reclamation plan as a form of minimization of such impacts, consistent with the guidelines developed under section 404(b)(1) of the Federal Water Pollution Control Act;
(C) consider financial assurances already required under applicable regulatory programs (including instruments such as surety bonds, collateral bonds, letters of credit, insurance, trust funds, and, where permitted, self-bonding) when determining the need for additional financial assurances; and
(D) allow the use, transfer, or sale of surplus compensatory mitigation credits generated through activities carried out under an approved reclamation plan, if such credits meet applicable environmental performance standards;
(7) encourage the use of off-site and out-of-kind mitigation options where appropriate; and
(8) include any other revisions determined appropriate by the Secretary.
(c) Guidance.--After issuing a final rule under this section, the Secretary shall issue guidance establishing objective, measurable success criteria for activities carried out under an approved reclamation plan for purposes of generating compensatory mitigation credits, and a phased credit release schedule tied to milestones for such activities.
(d) Definitions.--In this section:
(1) Approved reclamation plan.--The term "approved reclamation plan"--
(A) means--
(i) a reclamation plan approved pursuant to section 510 of the Surface Mining Control and Reclamation Act of 1977 (30 U.S.C. 1260);
(ii) a reclamation plan, plan of operations, or other similar plan approved by the Secretary of Agriculture or the Secretary of the Interior with respect to the mining or related operations of--
(I) minerals subject to location under the general mining laws;
(II) minerals subject to leasing under the mineral leasing laws; or
(III) mineral materials subject to disposition under the Act of July 31, 1947, commonly known as the Materials Act of 1947 (30 U.S.C. 601 et seq.);
(iii) a surface use plan of operations approved pursuant to subpart 3162 of title 43, Code of Federal Regulations (or a successor regulation);
(iv) a plan of operations or utilization plan approved pursuant to subpart 3200 of title 43, Code of Federal Regulations (or a successor regulation); and
(v) a plan of development approved pursuant to subpart 2805 of title 43, Code of Federal Regulations (or a successor regulation) that includes enforceable reclamation or surface restoration requirements; and
(B) includes a plan of operations approved under--
(i) subpart 3809 of title 43, Code of Federal Regulations (or a successor regulation); or
(ii) part 228 of title 36, Code of Federal Regulations (or a successor regulation).
(2) Secretary.--The term "Secretary" means the Secretary of the Army, acting through the Chief of Engineers.
The amendment was agreed to.
The text of the amendment is as follows:
Text printed in the Record (683 characters)
Add at the end the following:
SEC. __. STATE-LED PERMITTING EFFICIENCY AND WATER QUALITY
PILOT.
(a) In General.--The Administrator of the Environmental Protection Agency shall establish a voluntary pilot program to support State-led water quality improvements in waters listed as impaired for nitrogen or phosphorus under section 303(d) of the Federal Water Pollution Control Act (33 U.S.C. 1313(d)).
(b) Voluntary Participation.--Participation by agricultural producers in the program established under this section shall be voluntary.
(c) Savings Clause.--Nothing in this section may be construed to authorize the regulation of nonpoint sources or expand Federal jurisdiction.
The amendment was agreed to.
The text of the amendment is as follows: Add at the end the following:
Text printed in the Record (2,191 characters)
SEC. 22. INTERNATIONAL BOUNDARY AND WATER COMMISSION
AUTHORITY.
(a) Authorization.--The Commission is authorized to accept funds from a Federal or non-Federal entity, including through a grant or funding agreement, to study, design, construct, operate, or maintain wastewater treatment works, water conservation projects, or flood control works, and related structures, consistent with the functions of the Commission.
(b) Deposit.--Any funds accepted by the Commission under this section shall be--
(1) deposited into the account in the Treasury of the United States entitled "International Boundary and Water Commission, United States and Mexico"; and
(2) subject to the availability of appropriations, available until expended to carry out the activities described in subsection (a).
(c) Limitations.--
(1) Limit on reimbursement.--The Commission may not provide credit towards the non-Federal share of the cost of a project, or reimbursement, to non-Federal entities for funds accepted under this section in an amount that exceeds a total of $5,000,000 in any fiscal year.
(2) Source of funds.--The Commission may not accept funds under this section from any non-Federal entity--
(A) that is domiciled in, headquartered in, or organized under the laws of, or the principal place of business of which is located in, a foreign country of concern; or
(B) that has in place any agreement with a foreign country of concern.
(d) Report.--Not later than the last day of each fiscal year, the Commission shall submit to the Committee on Foreign Relations of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a report on the funds accepted under this section that includes a description of--
(1) the activities carried out with such funds; and
(2) costs associated with such activities.
(e) Definitions.--In this section:
(1) The term "Commission" means the United States Section of the International Boundary and Water Commission, United States and Mexico.
(2) The term "foreign country of concern" has the meaning given that term in section 10638 of the Research and Development, Competition, and Innovation Act (42 U.S.C. 19237).
There was no objection.
The amendment was agreed to.
The amendments were agreed to.
The bill was ordered to be engrossed and read a third time, and was read the third time.