Retainage limits in construction contracts

Summary#

HB 389, “An Act relating to retainage on public and private construction contracts,” would amend Alaska’s public contracting law and add a new section to state law on retainage. Its stated goal is to set rules for money withheld from construction payments until work is completed or another condition is met.

  • For private construction, it would cap retainage at 5% of each progress payment and 5% of the contract price in total. It would not require owners or contractors to withhold retainage.
  • If retainage is withheld, it must go into an interest-bearing escrow account, and the interest must be shared proportionately with the contractors and subcontractors it was withheld from.
  • It would set payment deadlines for private construction retainage, and impose a 2% penalty plus interest for late payment. A party owed the penalty may waive it.
  • For public construction, it would tie retainage payment deadlines and penalties to the new rules, and expressly apply those rules to political-subdivision contracts. It also changes the required subcontract terms and some notice requirements.
  • The bill applies to contracts entered into on or after its effective date. No effective date is provided in the supplied text.

What it means for you#

  • Private project owners: If you withhold retainage, you could not withhold more than 5% of a progress payment or 5% of the total contract price. You would generally have 30 days after the contractor satisfactorily completes the work to pay retainage, unless the contract sets a different period.
  • Private contractors: You would have to pay a subcontractor retainage within 10 days after you receive it from the owner or within 30 days after the subcontractor satisfactorily completes its work, whichever comes first. You could not withhold a higher percentage than the owner-contractor contract allows.
  • Private subcontractors: You would receive a share of interest earned on retainage withheld from you. If payment is late, the bill provides for a 2% penalty and interest at the prime rate. In a civil case under this section, a party that wins a money judgment would receive attorney fees under the bill’s formula.
  • Public agencies and construction businesses: Required public-contract subcontracts would have to include terms on payment of retainage and late-payment penalties and interest. For prime contractors, the bill also provides for a penalty and interest on retainage, including warranty retainage, owed by the state or a political subdivision.
  • Public subcontractors: The bill retains the requirement for payment for satisfactory work within eight working days after the payer receives the related payment. It changes the retainage deadline to the period in the new section or the end of a specified notice period, whichever is later.
  • General public: This bill concerns construction contract payments; it does not directly change taxes or create a public grant or benefit program.

Money#

No cost estimate or fiscal information is included in the supplied materials.

  • The bill requires retainage to be held in interest-bearing escrow, but gives no estimate of account or administration costs.
  • Late retainage payments could lead to a 2% penalty, interest, and attorney-fee awards in some civil cases.
  • The bill requires public contract terms and applies the new rules to political-subdivision contracts, but gives no estimate of staffing or other public costs.

What is unclear#

  • The supplied materials do not include the current versions of the amended statutes. I cannot verify all changes against current law, including the effects of repealing two existing provisions.
  • The new section is titled for private construction, but the bill also applies it to public contracts in some places. How all of its rules fit together for public contracts is not clear from the text.
  • For owner-to-contractor payment, the contract may set a different deadline from the general 30-day period. The bill does not set a limit on that alternative period.
  • “Satisfactory completion” is used but not defined in the new section. The bill does not set a process for deciding whether work is satisfactory.
  • The bill does not provide an effective date. Its rules would apply only to contracts entered into on or after that date.
  • HB 389 is introduced legislation, not law. The supplied text does not include funding, implementation rules, or an estimate of its cost.

Case for#

  • A 5% cap could limit how much of a contractor’s or subcontractor’s payment is held back at once and in total.
  • Escrow and proportional sharing of earned interest could help ensure withheld money and its interest reach the parties entitled to them.
  • Set payment deadlines could make it clearer when retainage is due, including when a subcontractor finishes before the owner pays the contractor.
  • A penalty and interest for late payment could give parties a financial reason to meet the deadlines.

Case against#

  • The bill sets no limit on a different owner-to-contractor deadline written into a contract, so the general 30-day payment rule may not control.
  • The public-contract provisions refer to a section framed as applying to private construction. Unclear interaction among the rules could make compliance harder to interpret.
  • The bill does not define “satisfactory completion” or establish a process for resolving disputes about it.
  • Escrow requirements, penalties, interest, and possible attorney fees could add costs or disputes; the supplied materials do not estimate their likely scale.