Summary#
On December 16, 2025, Calgary City Council passed Bylaw 174D2025 at third reading. It changes the land use district for 2803 – 30 Street SW in Killarney/Glengarry, Ward 8, from Direct Control to Residential – Grade-Oriented (R-CG). City staff’s stated goal was to allow more housing choices on the site.
- The change allows uses in the R-CG district, including rowhouses and townhouses, which the existing district did not list.
- The site is about 0.06 hectares (0.16 acres).
- A four-unit rowhouse proposal with secondary suites had been submitted for a separate development permit. This land-use decision does not itself approve that specific project.
What it means for you#
- Landowner: The site’s new district allows rowhouses and townhouses as uses. A development permit is still a separate step for a specific building.
- Nearby residents: One letter raised concerns about traffic, density, height, overshadowing and parking. City staff said building and site design, unit numbers and on-site parking would be assessed at the development-permit stage.
- General public: The decision changes the land-use rules for this parcel; it does not itself require construction.
Money#
City staff reported no anticipated financial impact from the land-use amendment; no separate cost estimate is provided.
What is unclear#
- The Council motion says the recommendation was adopted “after amendment,” but the supplied minutes do not say what was amended.
- The materials do not give the development permit’s later status or its final design, unit count or parking arrangement.
- The detailed rules that apply to development under the R-CG district are not included in the supplied material.
Case for#
- City staff say the change adds housing choices on a site that previously contained one dwelling unit.
- City staff describe the proposed increase in development options as modest and say the site is near a mobility corridor, transit and bikeways.
Case against#
- A letter to City staff objected on grounds of traffic, density, height, overshadowing and a shortage of parking in the area.
- The specific building design, number of units and on-site parking were left for the separate development-permit review, so those concerns were not settled by the land-use change itself.