Streets opened and a portion closed

Summary#

B26-0811, the “Opening of Streets, Designation of Opened Streets, and Closing of a Portion of a Street in Square 1112-E Act of 2026,” is a proposed stand-alone District law; it does not amend an existing Act in the supplied materials. It would open and name seven street segments in Square 1112-E and close part of 20th Street, S.E.; its stated goal is to support Phase 2 of the Hill East Master Plan.

  • The seven streets would be 20th Street, 21st Street, Burke Street, 20th Place, 21st Place, C Place, and C Street, all S.E.
  • The opened streets are for municipal purposes, contingent on the District Department of Transportation (DDOT) accepting them.
  • About 1,808 square feet of 20th Street, S.E., would close and revert to Lot 825.
  • The Department of General Services (DGS) is expected to build the streets with funding provided through the Deputy Mayor for Planning and Economic Development (DMPED). DDOT would take control and handle ongoing maintenance once the streets are complete.
  • The bill is at the introduced stage and is not law. Its stated start conditions include mayoral approval (or a Council override of a veto), a 30-day congressional review period, and publication in the D.C. Register.

What it means for you#

  • People who use streets in the area: The street layout would change when the new segments are built and opened, and part of 20th Street would close. The bill does not describe specific traffic, access, or route changes.
  • Nearby residents and the general public: The bill creates and names public streets, but it does not promise a particular service level or say how the changes would affect nearby residents.
  • DGS and DDOT: DGS is expected to build the street segments. After completion, DDOT would assume control and responsibility for maintenance.
  • Taxpayers: Public budgets would support construction and later maintenance. The materials do not identify a new tax or fee.
  • Developers or property owners: The materials link the streets to development of properties disposed for private development in 2022, but the bill does not set out new duties for developers or require them to apply for approval.

Money#

The fiscal statement says funds are sufficient in the fiscal year 2026 budget and proposed fiscal years 2027–2030 plan to implement the bill, but gives no separate construction-cost estimate for these streets.

  • DGS is expected to build the street segments using funding provided through DMPED.
  • DMPED’s Hill East capital plan includes more than $62 million for infrastructure in fiscal years 2026–2032. That figure covers Hill East infrastructure, not just these streets.
  • DDOT estimates maintenance for these roadways at about $1 million, with maintenance expected every five years. The first maintenance is expected around 2034.

What is unclear#

  • The supplied materials do not give a detailed schedule beyond DGS’s expectation that the streets will be completed by the end of 2028.
  • They do not explain how DDOT will decide whether to accept the streets, or what happens if it does not accept them.
  • They do not describe how the street closure and new layout would affect nearby access or traffic.
  • The materials do not explain the practical or property effects of the closed segment reverting to Lot 825.

Case for#

  • The bill appears intended to provide streets needed to support Phase 2 of the Hill East Master Plan and development in the area.
  • Naming and opening the street segments could establish a public street network in the planned area.
  • The fiscal statement says existing budget and financial-plan funds are sufficient, and identifies a path for construction and later maintenance.

Case against#

  • A possible trade-off is that public funds would pay for construction and ongoing maintenance of streets linked to private development.
  • The bill does not explain the effects of closing part of 20th Street on people who use the area.
  • The materials do not spell out the acceptance process or what happens if DDOT does not accept the completed streets.