Summary#
Edmonton City Council approved a work plan update for changes to the City’s review of EPCOR Water Services Inc.’s performance-based regulation (PBR) applications. The goal is to improve how the City reviews proposed water and wastewater rates, utility performance and related information; this decision does not approve EPCOR’s 2028–2031 rates or application.
- City staff must advance proposed changes to PBR principles and outcomes, and to roles, responsibilities and accountabilities.
- Staff must return to Utility Committee with options for adding two industry professionals to the Committee and for letting the Utility Advisor ask direct questions at meetings focused on PBR.
- Staff must advance proposed changes to performance measures and how performance is measured.
- Recommendations 4 and 5 are for a later phase, with planning to require more staff and Committee resources. Staff must also report back with possible alternatives to the proposed penalty framework after Council removed recommendation 9.
- Council approved the Committee’s recommendations without debate on September 8, 2026, by a vote of 12–0.
What it means for you#
- Water and wastewater customers: This changes the City’s review process, not your rates directly. The decision does not set new rates or guarantee a particular rate outcome.
- EPCOR Water Services: Its 2028–2031 application is due to the City by November 30, 2026. Some process changes may apply to that application; staff expect more significant changes later or during that PBR term.
- Utility Committee and City staff: They must work on the specified changes and return with options and a report on the penalty framework. The decision does not set a full implementation schedule or require that the proposed Committee changes be adopted as written.
Money#
The changes are expected to need extra funding, but no total cost is available.
- City staff say external consulting support and permanent staffing are needed, including up to two full-time-equivalent staff in City Administration and more resources for Utility Committee’s regulatory expertise.
- Possible funding sources include water and wastewater rates or a funding request in the 2027–2030 operating budget. Council must approve any additional funding before staff proceed with process changes.
What is unclear#
- The cost of consulting, staff and Committee resources, and how any costs would be split or recovered through rates, are not settled.
- The decision does not set a timeline for implementation or say which changes will be ready for the 2028–2031 application.
- The options for adding industry professionals and giving the Utility Advisor direct-question powers have not been decided.
- The details of recommendations 4–8 and the alternative penalty framework are not included in the decision text.
Case for#
- City staff say the current model has been effective but needs incremental improvements as PBR applications become more complex.
- The proposed work aims to strengthen the City’s review of rates, capital plans and utility performance, while clarifying who is responsible for each part of the process.
- The two-industry-professional and direct-question options could add expertise and allow more detailed questioning during Committee review, if adopted.
Case against#
- The work requires added staff, consulting and Committee resources, but the cost and funding source are not settled; some costs might be recovered through utility rates.
- Several important choices remain for later reports, so the decision does not yet establish how the new review process will work in practice.
- Council removed the proposed penalty-framework recommendation and asked for alternatives, leaving unclear how poor performance could lead to penalties or other corrective action.