Public works could base contracts on provable costs

Summary#

Assembly Bill 3 would amend Nevada’s public-works law, NRS 341.161; it would not create a separate law or agency. Its stated goal is to revise procedures for certain construction contracts. The bill is prefiled and is not law.

  • The State Public Works Board would have to adopt procedures that allow a construction contract to be awarded based on either the project’s final cost or a provable cost for part of the project, with the contractor guaranteeing that the applicable cost will not be exceeded.
  • The Board’s regulations must also cover contractor qualifications, bidding and awards, and project scheduling and control. The bill does not replace those requirements.
  • The Administrator may let a contract for services to help the Division design and build a capital-improvement project, but the bill does not require the Administrator to use this contract approach.
  • The bill does not create a new public right, tax, fee, or benefit.

What it means for you#

  • State Public Works Board and Division: The Board must set procedures that include the option to base a construction contract on a provable cost for part of a project. The bill does not require that option to be used for any particular project.
  • Contractors: The cost guarantee applies to the cost basis used for the contract. The bill does not define “provable cost.”
  • People who use public services: The bill does not directly change a service, public-works project, or eligibility for public services. Any practical effect would depend on how the Board’s procedures are written and used.

Money#

The fiscal note says the bill may affect state finances; it lists no effect on local government or the State Highway Fund.

  • No cost estimate is provided. The bill does not appropriate a specific amount.
  • The bill requires the Board to adopt regulations, but the materials do not say what staffing or other resources that will require.

What is unclear#

  • “Provable cost” is not defined, and the bill gives no test for deciding whether a cost qualifies.
  • The bill does not explain how a cost guarantee for part of a project would relate to costs for the rest of that project.
  • The bill does not set deadlines or spell out the details of the Board’s procedures.
  • The supplied materials do not include the full current text of NRS 341.161. The legislative digest says current law provides for procedures based on a guaranteed final project cost, but I could not verify the existing law’s full requirements or current practice against the statute.

Case for#

  • A possible argument for the bill is that some project costs may be provable for only part of a project. Allowing procedures for a guarantee on that portion could give the state another way to award construction contracts.
  • The bill retains the requirement for a contractor’s guarantee that the applicable cost will not be exceeded.
  • The Board must set procedures, rather than the bill itself prescribing how every contract must be awarded.

Case against#

  • The bill does not define “provable cost” or explain how the Board should assess it, leaving an important part of the new option to later regulations.
  • A guarantee covering only part of a project may leave questions about how the remaining costs are handled; the bill does not answer them.
  • The state may incur costs to make and carry out the required procedures, but the materials give no estimate.