Summary#
Introduction 1032-2026, sponsored by Council Member Amanda C. Farías, would create a local-law duty for the Department of Transportation (DOT) to study ferry service to and from City Island and report its findings. Its stated approach is to assess whether a ferry landing is feasible. The bill is laid over in two committees and is not law.
- DOT must consult the small business services commissioner, the environmental protection commissioner, and any contracted entity that provides or administers economic development benefits for the city.
- The study must assess potential sites, required permits and approvals, water depth and access, environmental effects, effects on businesses and commuters, costs, and each site’s suitability.
- DOT must send the report to the Mayor and Council Speaker and post it online within one year after the law takes effect.
- If the report finds any site suitable, DOT must choose one and begin designing and building a landing within one year after submitting the report. It must start ferry service when construction is complete.
What it means for you#
- City Island residents, commuters and businesses: The bill does not guarantee a particular site or service schedule. But if the report finds a suitable site, it requires DOT to select one, begin design and construction, and start service once the landing is complete.
- DOT: It would have to carry out the study and reporting duties, and the conditional construction and service duties.
- Status: The bill had committee hearings on October 20, 2026, and was laid over in both committees. It has not been passed.
Money#
The bill gives no estimate of the cost of the study, landing or ferry service.
- The study must estimate initial construction costs and annual operating costs for each potential site.
- The bill does not specify funding, who would operate the service, or its fares.
What is unclear#
- The bill does not set criteria for deciding whether a site is suitable or how DOT must choose among suitable sites.
- It does not specify the ferry route, schedule, fares, operator, or when construction must be completed.
- It does not require public consultation or say how the city would fund construction and service.
Case for#
- The bill would require the city to examine permits, access, environmental effects, effects on local businesses and commuters, and costs before selecting a site.
- Requiring service if a site is found suitable could carry the study’s result into action rather than ending with a report.
Case against#
- One concern is that a finding of suitability triggers a duty to begin design and construction, but the bill sets no funding plan or further approval step.
- It leaves key choices—including the suitability criteria and the service’s route and schedule—to be worked out later.