Timeframes for agency approvals and change orders on small capital projects

Summary#

Introduction 1064-2026, sponsored by Council Member Carl Wilson, would amend the New York City Administrative Code. It would require the Department of Design and Construction (DDC) to set and publish timeframes for agency approvals and decisions on change order requests for certain small capital projects; the stated aim is to minimize project delays. The bill was laid over in the Contracts Committee on October 29, 2026, and is not law.

  • It covers city construction or design-services contracts for capital projects with an estimated construction cost of no more than $10 million, as determined in the project scope.
  • DDC must consult the Mayor’s Office of Contract Services and other relevant agencies, publish the timeframes online, distribute them to contracting agencies, and review them at least once every two years.
  • If an agency misses a timeframe, it must, within 10 days after the timeframe expires, send the contractor a written explanation signed by the agency commissioner. It must state the reason for the delay and the date the agency expects to act.
  • The law would take effect one year after it becomes law.

What it means for you#

  • Contractors: For covered projects, you would get an explanation and expected action date if an agency misses a timeframe. The bill does not require the agency to approve the work or grant a change order.
  • City agencies and DDC: DDC must set and maintain the timeframes. A contracting agency that misses one must provide the required explanation. The bill does not set the timeframes itself.
  • Other residents and businesses: The bill does not directly change your rights, fees, or services.

Money#

No cost information is in the available material.

  • The bill requires DDC to set, publish, distribute, and review timeframes, but gives no staffing or cost estimate.

What is unclear#

  • The bill does not say what timeframes DDC must set or how it must choose them.
  • It sets no penalty or other remedy if an agency misses a timeframe or fails to send the required explanation.
  • It does not explain how “other relevant agencies” will be identified or how contractors can raise concerns about a missed deadline.
  • The bill has not passed; its passage and eventual implementation are uncertain.

Case for#

  • The bill’s stated aim is to minimize delays on smaller capital projects. Setting timeframes could give agencies and contractors clearer expectations.
  • Requiring an explanation, a reason for delay, and an expected action date could make missed timeframes more visible to contractors.

Case against#

  • The bill does not itself set deadlines. The practical effect will depend on the timeframes DDC later establishes.
  • A missed timeframe would require an explanation, but the bill does not require the agency to finish the approval or change order by the date it gives, or provide a remedy to the contractor.