Summary#
Int 1085-2026, sponsored by Council Member Farah N. Louis, is a proposed local law amending the New York City Administrative Code rules on fees for buildings in the Alternative Enforcement Program. The Council summary describes higher fees for buildings not discharged from the program within four months, but the bill’s operative text does not include that four-month condition. The bill is introduced and waiting in committee; it is not law.
- The Department of Housing Preservation and Development (HPD) would have to set a fee schedule by rule. The schedule must include minimum fees for specified inspections and related work.
- For building-wide inspections, repair monitoring and reassessment, the schedule must include at least $1,000 per dwelling unit every six months, starting on the inspection date, and a maximum total fee of at least $2,000 per dwelling unit during program participation.
- It must also include at least $500 for each complaint-based inspection that results in a class B or class C violation, and at least $150 per building for each failed reinspection after an owner certifies corrections.
- The law would take effect 180 days after it becomes law.
What it means for you#
- Building owners in the program: The text makes owners who have been notified of participation subject to fees for inspections, reinspections and other department actions while their building remains in the program. The amounts would be set by HPD rules, but could not be below the listed minimums.
- Tenants and residents: The bill does not directly create a tenant fee or change tenant rights.
- HPD: The department would have to issue the fee schedule. The bill does not specify how or when it must do so.
Money#
No cost or revenue estimate is provided.
- Owners would pay fees under the schedule; the bill sets minimum amounts but does not state the resulting total costs.
- The materials give no estimate of city revenue or HPD’s costs to administer the changes.
What is unclear#
- The bill’s text does not limit the increased fees to buildings still in the program after four months, despite the title and Council summary.
- The current Administrative Code text was not supplied, so the existing fee amounts and how much would change cannot be verified.
- HPD’s future rules would set the actual fees. The bill does not give a deadline for those rules.
- The phrase “maximum total fee of at least $2,000” does not clearly state the actual maximum fee.
Case for#
- The Council summary presents the bill as increasing charges for buildings that remain in the program beyond four months. A possible rationale is that higher fees could encourage owners to complete required work and leave the program sooner.
Case against#
- The bill’s operative text does not include the four-month limit described in the summary. As written, its fee requirements apply during program participation.
- Minimum fees based on dwelling units and repeated inspections could add substantial costs for owners; the bill provides no estimate of those costs.
- HPD would set the actual fees, and the bill does not clearly state the total maximum charge.