Rodent abatement during certain construction work

Summary#

Introduction 1141-2026, sponsored by Council Member Crystal Hudson, would amend New York City’s Administrative Code by adding rules for some construction work and changing the section on private sewers and drains. Its stated goal is to require rodent abatement during that work; it is not law and is waiting in committee.

  • The Department of Environmental Protection (DEP) commissioner would have to retain two licensed exterminators for DEP construction work estimated to take at least three days and planned to go deeper than 10 feet. One must survey the site; the other must carry out a rodent abatement plan that meets Department of Health and Mental Hygiene requirements.
  • The exterminator carrying out the plan must continue rodent abatement weekly until the construction is complete.
  • For that DEP work, the commissioner must give adjacent property owners written notice describing the abatement efforts at least five days before the scheduled start.
  • A person applying for a permit to construct or connect private sewers or drains would have to certify that two licensed exterminators have been retained, with one surveying the site and one implementing a plan. Weekly abatement would be required until the work is complete.
  • Private-work permit holders must give adjacent property owners written notice describing the abatement efforts at least five days before the scheduled start.

What it means for you#

  • Nearby property owners: For covered DEP work and private sewer or drain work, you would receive written notice describing rodent abatement efforts. The bill does not require notice for other construction work.
  • People doing private sewer or drain work: Before getting a permit, you would have to certify that you retained two licensed exterminators. The text does not set a minimum project length or depth for this requirement.
  • DEP: The commissioner would have to retain exterminators for DEP projects only when both the duration and depth conditions are met.
  • The bill does not create a new agency, set a fine, or specify an application, appeal, or reporting process. It says the commissioner may revoke a private-work permit, but the materials do not show whether that power is new or how current law compares.

Money#

No cost information is in the available material.

  • DEP would have to retain two exterminators for covered projects, but the bill gives no staffing or cost estimate.
  • Private permit applicants would have to retain two exterminators. The bill does not state who pays or estimate the cost.

What is unclear#

  • The supplied material does not include the current text of the amended private-sewer section, so the changes to existing permit rules cannot be fully verified.
  • The bill does not define “licensed exterminator” or explain how the required plan is developed or checked.
  • For private work, notice is required upon permit issuance and at least five days before the scheduled start; the bill does not explain what happens if a permit is issued less than five days before work is due to start.
  • The bill does not specify oversight, penalties for failing to meet the new requirements, or how these rules interact with other rodent-abatement requirements.

Case for#

  • The bill’s design could address rodent infestation at construction sites by requiring a survey and abatement plan before covered work begins.
  • Weekly abatement through the end of construction could maintain treatment while work is underway.
  • Advance notice would tell adjacent property owners what abatement efforts are being conducted.

Case against#

  • One concern is that retaining two exterminators and carrying out weekly abatement could add costs and coordination demands; the bill gives no estimate.
  • Private sewer and drain work would face these requirements regardless of its duration or depth, unlike the stated threshold for DEP work.
  • The bill does not explain how plans will be checked or what happens if required abatement or notice is not provided.