Grant permanent and expanded Design-Build authority to all New York City agencies

Summary#

Res. 0264-2026 is a New York City Council resolution sponsored by Council Member Linda Lee. It calls on the New York State Legislature to pass, and the Governor to sign, a state law giving all New York City agencies permanent and expanded authority to use design-build (one contract covering design and construction). It does not change city law or bind the state.

  • The resolution says state law currently allows only certain city agencies to use design-build, including the Departments of Design and Construction, Environmental Protection, Transportation, and Parks and Recreation, plus Health + Hospitals, the School Construction Authority, and NYCHA.
  • The Council held committee hearings on April 29, 2026, and laid the resolution over in three committees. It remains under consideration; it has not been adopted.

What it means for you#

  • City residents and taxpayers: The resolution itself does not change projects, services, taxes, fees, or agency powers. If the state acts, more city agencies could be allowed to use design-build, but the resolution does not itself authorize them to do so.
  • City agencies: The resolution asks for authority for all agencies, but does not set rules for how they would use it.

Money#

No publicly available information on the cost of the state legislation the resolution asks for.

  • The resolution does not appropriate money or impose a fee.
  • It cites the City’s reported estimate that 42 current design-build projects were expected to save $1.4 billion and 50 years of project time, with anticipated costs 10 percent lower than under the traditional lowest-bidder approach. These are claims cited by the resolution, not a cost estimate for expanding authority.

What is unclear#

  • The resolution does not provide proposed state-law text, so the conditions, safeguards, and oversight for expanded authority are unknown.
  • It does not say when state legislation might be introduced or take effect.

Case for#

  • The resolution says design-build combines design and construction in one contract, with the design-builder responsible for most design work and all construction activities.
  • It cites the City’s reported savings and faster timelines for current projects as a reason to expand the method.
  • The resolution argues that agencies without this authority may face delays, cost overruns, and procurement challenges.

Case against#

  • The resolution does not describe safeguards for cost, quality, or oversight under expanded authority, so those protections cannot be assessed from this material.
  • The savings and time figures it cites concern current projects; the resolution does not show whether similar results would apply across all agencies and projects.