Summary#
Res. 0264-2026 is a New York City Council resolution sponsored by Council Member Linda Lee. It calls on the New York State Legislature to pass, and the Governor to sign, a state law giving all New York City agencies permanent and expanded authority to use design-build (one contract covering design and construction). It does not change city law or bind the state.
- The resolution says state law currently allows only certain city agencies to use design-build, including the Departments of Design and Construction, Environmental Protection, Transportation, and Parks and Recreation, plus Health + Hospitals, the School Construction Authority, and NYCHA.
- The Council held committee hearings on April 29, 2026, and laid the resolution over in three committees. It remains under consideration; it has not been adopted.
What it means for you#
- City residents and taxpayers: The resolution itself does not change projects, services, taxes, fees, or agency powers. If the state acts, more city agencies could be allowed to use design-build, but the resolution does not itself authorize them to do so.
- City agencies: The resolution asks for authority for all agencies, but does not set rules for how they would use it.
Money#
No publicly available information on the cost of the state legislation the resolution asks for.
- The resolution does not appropriate money or impose a fee.
- It cites the City’s reported estimate that 42 current design-build projects were expected to save $1.4 billion and 50 years of project time, with anticipated costs 10 percent lower than under the traditional lowest-bidder approach. These are claims cited by the resolution, not a cost estimate for expanding authority.
What is unclear#
- The resolution does not provide proposed state-law text, so the conditions, safeguards, and oversight for expanded authority are unknown.
- It does not say when state legislation might be introduced or take effect.
Case for#
- The resolution says design-build combines design and construction in one contract, with the design-builder responsible for most design work and all construction activities.
- It cites the City’s reported savings and faster timelines for current projects as a reason to expand the method.
- The resolution argues that agencies without this authority may face delays, cost overruns, and procurement challenges.
Case against#
- The resolution does not describe safeguards for cost, quality, or oversight under expanded authority, so those protections cannot be assessed from this material.
- The savings and time figures it cites concern current projects; the resolution does not show whether similar results would apply across all agencies and projects.