Summary#

Res 0422-2026 is a New York City Council resolution, not a change to city law. Prime sponsor Sandy Nurse and the other sponsors call on the New York State Public Service Commission (PSC) to issue an emergency rule restricting Con Edison’s use of its interconnection methodology for battery storage facilities in networks it deems constrained. The stated goal is to address higher interconnection costs and support battery storage.

  • The resolution asks the PSC to act; it does not itself restrict Con Edison or require the PSC to issue a rule.
  • The resolution’s recitals say Con Edison’s methodology increased costs for affected facilities by more than 25 times.
  • The Council referred the resolution to committee on April 16, 2026. It is waiting in committee; no hearing or vote is listed.

What it means for you#

  • Battery storage developers: The resolution would not change your costs or Con Edison’s rules. If the PSC acts, the effect would depend on the rule it issues.
  • Residents and businesses: It does not directly change electricity bills, service, or legal rights.
  • Con Edison and the PSC: The resolution asks the PSC to restrict Con Edison’s use of its methodology. It does not bind either one.

Money#

No cost information is in the available material.

  • The resolution itself does not appropriate money or set fees.
  • Its recitals report that Con Edison’s methodology raised interconnection costs for affected battery projects by more than 25 times; the resolution does not set or change those charges.

What is unclear#

  • The resolution does not specify what restrictions the PSC should impose or when they should take effect.
  • It does not define which networks are “constrained” or how a future rule should treat particular projects.
  • It does not say whether the PSC will act, or what costs or other effects a rule might have.

Case for#

  • The resolution’s recitals say battery storage can supply power during peak demand and reduce reliance on polluting power plants.
  • The recitals report that Con Edison’s methodology sharply raised costs and describe concerns from NY-BEST and NYSEIA that its assumptions about battery charging and project construction are flawed.
  • The sponsors’ requested approach would leave the PSC to issue a rule, rather than having the Council set detailed utility requirements.

Case against#

  • Con Edison’s rationale, as described in the resolution, is that battery projects in constrained networks could exceed local substations’ demand capacity and threaten reliability.
  • The resolution does not set out how to weigh that reliability concern against the goal of lowering interconnection costs.
  • Because the requested rule is unspecified, developers, Con Edison and the public cannot tell from the resolution what restrictions would apply.