Summary#
Res. 0693-2026 is a City Council resolution, not a local law. Prime sponsor Crystal Hudson and the other sponsors ask the New York State Legislature to pass S.9144/A.10141 and the Governor to sign it; the Council resolution itself does not change the law or bind anyone. The stated goal is to pause new data-center permits while the state studies environmental effects and utility costs.
- The state bill, as described in the resolution, would pause permits for new data centers for at least 3 years and 90 days.
- It would require the state Department of Environmental Conservation to issue a generic environmental impact statement within 18 months and make needed environmental rules within 3 years.
- It would require the state Public Service Commission to report on data centers’ effects on utility rates no less than 18 months after the bill becomes law, and issue orders to ensure the facilities bear the costs of electric and gas service.
- The resolution was introduced and referred to a City Council committee on October 22, 2026. It is waiting in that committee; no Council vote is recorded.
What it means for you#
- New York City residents and utility customers: The resolution would not change your bills. If the state bill became law, it would require state action on data centers’ environmental effects and utility costs.
- Data-center developers: The resolution would not affect permits. If the state bill became law, it would impose a permit moratorium on new data centers statewide for at least 3 years and 90 days.
- New York City government: The resolution asks the state to act; it gives no new duties or powers to a city agency.
Money#
No cost information is in the available material.
- The resolution itself does not authorize spending or set fees.
- It describes a state bill that would require state studies, a report and regulatory work, but gives no cost estimate.
What is unclear#
- The resolution’s title and final request attribute orders to make data centers bear added utility costs to the Department of Environmental Conservation. Its detailed description instead assigns the rate report and cost-related orders to the Public Service Commission. The state bill text is not supplied, so that conflict cannot be checked.
- The resolution does not explain which permits would be covered, or whether exceptions would apply.
- The resolution does not give the state bill’s start date or explain how the moratorium would end.
- The resolution does not specify how the state would determine which costs are attributable to data centers.
Case for#
- The sponsors’ resolution argues that data centers could increase electricity demand, strain grid capacity and raise costs for other utility customers.
- It also points to noise, water use and air pollution as potential local harms.
- A temporary permit pause could give the state time to study these effects and set environmental rules before more facilities are approved.
Case against#
- A statewide moratorium lasting at least 3 years and 90 days would cover new data centers broadly; the resolution does not describe exceptions based on a project’s size or impact.
- The resolution does not explain how the state would separate costs caused by data centers from other utility costs, or how it would apply the requirement that facilities bear those costs.
- The mismatch over which state agency would issue cost-related orders leaves an important part of the proposal unclear.