The Civics Project

Utilities Must Explain Need for Power Lines

Summary#

Utilities seeking approval for certain transmission lines would have to explain why grid-enhancing technologies in existing routes cannot meet the need, and the State Corporation Commission would have to verify the utility’s reliability analyses. SB 862 would amend a section of Virginia’s Code of Virginia governing approval of electric utility facilities and transmission lines.

  • The requirements apply to transmission lines of 138 kilovolts or more that need Commission approval; the bill does not require approval for lines that do not need a certificate of public convenience and necessity.
  • The Commission would have to check the utility’s load-flow models, contingency analyses and stated reliability needs when deciding whether a line is needed.
  • In choosing a route, the Commission would have to consider cultural resources identified by federally recognized Tribal Nations, along with other listed effects.
  • The bill would not require utilities to use grid-enhancing technologies; it would require an explanation of why those technologies in existing transmission routes cannot meet the need.

What it means for you#

  • Electric utilities: Applicants for covered lines would have to include the grid-enhancing-technology explanation and reliability analyses in their applications.
  • People and communities near a proposed route: The Commission would consider the listed effects when deciding whether to approve a line and its route. The bill does not set out a new application or hearing process for residents.
  • Federally recognized Tribal Nations: The Commission would consider cultural resources they identify, but the bill does not specify how they would identify resources or take part in the decision.
  • Electric customers: The bill does not directly change electricity rates, bills or service.

Money#

No cost estimate or funding amount is stated in the bill.

  • The bill does not set a fee or provide funding for the Commission’s review.

What is unclear#

  • The bill uses a definition of “grid-enhancing technologies” in another section of Virginia law; the technologies covered are not listed here.
  • The bill does not set a standard for the utility’s explanation or describe how the Commission must verify the analyses.
  • The bill amends and reenacts an existing rule; how much of its wording would be new is unclear.
  • The bill gives no start date. It is introduced legislation, so passage is uncertain.

Case for#

  • Requiring utilities to explain why grid-enhancing technologies cannot meet a need could prompt a serious look at using existing transmission routes before building new lines. That could help avoid some land and community impacts.
  • Requiring the Commission to verify reliability analyses gives it a direct check on the evidence utilities use to justify a line. That could make approval decisions more dependable than relying on the utility’s case alone.

Case against#

  • Requiring a technology comparison and verification could add technical work before a line is approved. If the Commission’s review takes longer, communities and utilities may wait longer for a decision about needed transmission.
  • The bill requires an explanation of why grid-enhancing technologies would not meet the need, but does not require utilities to use them when they could. That leaves the final choice to build a line even when alternatives may be available.