Arkansas SB-65 is an enacted appropriation law for the Department of Shared Administrative Services (DAS), for its Office of State Technology. It does not amend a general statute; it reappropriates the balance of an appropriation in Act 777 of 2025 for replacing the uninterruptible power supply (UPS) at the State Data Center West. The stated purpose is to fund that replacement.

  • DAS may use up to $1,357,050 from the Sustainable Building Design Revolving Loan Fund for the project, starting July 1, 2026.
  • Contracts and other obligations cannot exceed State Treasury funds actually available for the project. Grants, donations, federal funds, and the agency’s unobligated cash income or funds may supplement those funds.
  • The appropriation must follow state purchasing and fiscal-control laws. DAS may not use its maintenance and general operations appropriations for this project.

What it means for you#

  • DAS and the Office of State Technology: The law makes funds available for the UPS replacement at the Data Center West facility at 1105 Anderson Drive in Little Rock. It does not set a completion date or describe the equipment to be installed.
  • Taxpayers and the public: The law authorizes project spending but does not create a new tax, fee, benefit, or direct service for the public.

Money#

The act reappropriates up to $1,357,050; that is an appropriation limit, not a reported final project cost.

  • The funds are payable from the Sustainable Building Design Revolving Loan Fund.
  • The act allows grants, donations, federal funds, and unobligated agency cash or funds to supplement State Treasury funds.
  • No publicly available information is provided about the project’s final cost or how much of the earlier appropriation has already been spent.

What is unclear#

  • The supplied material does not include Act 777 of 2025, so the earlier appropriation’s full terms and the remaining balance cannot be verified.
  • The act does not give a project cost breakdown, equipment specifications, procurement schedule, or completion deadline.
  • It does not say whether the authorized amount will cover the full project or whether supplemental funds will be needed.

Case for#

  • A possible argument for the act is that it keeps capital funding available for a specific equipment replacement at a state data center.
  • It sets a spending ceiling and requires compliance with existing purchasing and fiscal-control laws.
  • It bars using the agency’s maintenance and general operations appropriations for this project.

Case against#

  • The act does not provide enough detail to assess whether the amount is reasonable for the equipment and work planned.
  • It does not explain how much of the earlier appropriation remains or whether the cap will cover the full project.
  • The act requires an effective date of July 1, 2026, but gives no project completion deadline.

Votes

The recorded vote on this bill, member by member.

  1. Division No. 1687520

    Passed34 members voted

    Third Reading

    FOR · 34

    Each dot is one member. Hover or tap one to see who.

    34For

    • Republican28
    • Democratic6

    0Against