Noise barrier funding from toll credits

Summary#

SB 152 would add a new section to New Hampshire’s RSA 228 and amend RSA 6:12 to recognize a new noise barrier construction fund. Its stated goal is to fund the design and construction of noise barrier projects. The supplied status says the bill was referred to interim study on January 7, 2026; it is not law.

  • The transportation commissioner could sell up to $10 million in turnpike toll credits per year, but only if enough credits remain for the state match for federal apportionments over a five-year period.
  • Each sale would need approval from the General Court’s Fiscal Committee and Joint Legislative Capital Project Overview Committee.
  • Sale proceeds would go into a restricted, nonlapsing fund and be continuously appropriated to the Department of Transportation (DOT). Spending from the fund would also need approval from both committees.
  • The commissioner could use the money for projects meeting the state’s Type II highway noise barrier criteria, and may consider additional authorized eligibility factors after consulting an affected community about impacts.

What it means for you#

  • People and communities near highways: The bill would not give residents a right to a barrier or require DOT to build one. It would create a possible funding source for qualifying projects. The bill calls for consultation with an affected community before the commissioner considers additional authorized eligibility factors; it does not require community consent.
  • DOT: The commissioner would decide whether to sell credits and could use fund money for eligible projects, subject to the stated conditions and approvals.
  • State government and taxpayers: The bill creates a new fund and authorizes a potential source of revenue. It does not set a guaranteed amount of revenue or require a sale.
  • Current law: The materials do not include the existing text of RSA 228, RSA 6:12, or the DOT noise barrier policy, so I could not verify how the bill’s proposed rules compare with current law.

Money#

The fiscal note says the bill’s state revenue and spending effects are indeterminable after FY 2025.

  • The bill allows sales of up to $10 million in toll credits per year, if the five-year state-match condition is met and both committees approve.
  • Sale proceeds would be continuously appropriated to DOT, but the bill does not set a total fund amount or require the commissioner to sell credits.
  • The fiscal note estimates $0 impact in FY 2025 and indeterminable impact for FY 2026–2028. DOT said there was no federal authority or marketplace setup for selling turnpike toll credits at the time of its assessment.

What is unclear#

  • The materials do not explain how toll-credit sales would work if federal authority or a marketplace became available.
  • The bill does not set project application rules, selection criteria beyond the referenced Type II policy, timelines, appeals, or reporting requirements.
  • It does not define “additional authorized adjustment factors.” The referenced DOT policy is not included, so its criteria and any current process cannot be checked.
  • The materials do not explain how the fund’s use would interact with existing noise barrier funding or projects.
  • The bill states an effective date of July 1, 2025, but the supplied status shows it was referred to interim study in January 2026. No enactment is shown in the supplied material.

Case for#

  • A dedicated fund could provide money specifically for designing and building qualifying noise barriers.
  • Allowing sales only when enough toll credits remain for the stated five-year federal-match calculation could limit sales when credits are needed for that purpose.
  • Requiring approval from two legislative committees for both sales and spending provides checks on the commissioner’s discretion.
  • Consultation with an affected community could let the commissioner consider community impacts when considering additional eligibility factors.

Case against#

  • The bill creates no guaranteed revenue, and the fiscal note says the toll-credit sale mechanism was not available at the time of its assessment. The fund could therefore receive little or no money.
  • The bill leaves project selection procedures and the additional eligibility factors unclear. This could make it hard for communities to know how projects would be chosen.
  • Committee approval is required, but the bill does not specify timelines or how decisions would be made public.
  • The bill creates a new funding route without explaining how it would fit with existing noise barrier projects or funding sources.