Tolls expanded to fund turnpike projects

Summary#

HB 2026 is an enacted New Hampshire law. It adopts the state’s 2027–2036 transportation plan, changes toll rates under RSA 237:9, repeals an existing toll-discount provision in RSA 237:11, and authorizes easement transfers for the Gregg Mill Road Bridge in New Boston. Its stated goal is to support the plan’s turnpike projects and related operating and maintenance costs.

  • The plan includes named road projects and funding amounts, including I-93 work in Bow and Concord ($285.8 million) and I-293 Exit 6 and Exit 7 work in Manchester (about $221.8 million combined). The law encourages prompt implementation; it does not itself say every project must be completed.
  • Starting January 1, 2027, it sets toll schedules at seven plazas for 12 vehicle classes. Cash and vehicles without a funded New Hampshire E-ZPass account have one schedule; funded E-ZPass accounts have listed minimum rates.
  • It repeals the existing statutory E-ZPass discount on established tolls. For 210 days starting December 1, 2026, the Department of Transportation must provide a free New Hampshire E-ZPass transponder if a new or current account holder requests one.
  • The state must transfer specified permanent easements and a temporary construction easement to New Boston for bridge reconstruction. The town and the Department of Natural and Cultural Resources may agree to further transfers needed for the project.
  • The state must receive full fair market value for transferred interests, based on an approved appraisal. Replacement land may be accepted if all parties with an interest agree.

What it means for you#

  • Turnpike users: The scheduled rates depend on plaza, vehicle class, and payment type. For a Class 1 vehicle, cash rates range from $1 at Hooksett Ramp to $4 at Hampton Main. The listed minimums for a funded E-ZPass account range from $0.35 to $1.40 at those same plazas. Other vehicle classes have different rates. The bill does not provide the prior rates, so the size of each increase cannot be verified from the supplied material.
  • E-ZPass account holders: The department must issue a free transponder on request during the 210-day period beginning December 1, 2026. The bill does not say what happens to transponder charges after that period.
  • New Boston: The town receives specified easements for bridge reconstruction and may agree with the state to further transfers needed for the project. The town must provide compensation unless the parties agree to replacement land.
  • Transportation projects: The law adds named projects and amounts to the 2027–2036 plan. It does not create a general right to road improvements or require the public to apply for them.
  • Taxpayers: The law does not impose a new tax. It directs toll revenue to turnpike purposes, and existing law in the amended text allows highway-fund or general-fund money to cover certain bond-payment shortfalls, with repayment from toll collections when available.

Money#

No overall cost estimate is available in the supplied material.

  • The plan lists project amounts, including $6.8 million for Albany, $146.9 million and $74.9 million for Manchester projects, and $68.5 million for a group of 11 projects. These are plan amounts, not a separate cost estimate for the law.
  • Toll revenue is to be used for turnpike system costs, including operations, construction, reconstruction, and maintenance, and for bond payments as described in existing law.
  • Free transponders are required during the specified period, but the law gives no cost or staffing estimate.
  • The state must receive fair market value for the New Boston easements; the amount is not stated.

What is unclear#

  • The bill’s title and analysis refer to periodic toll adjustments tied to a projected inflation index. The supplied operative text sets rates beginning in 2027 but does not show a periodic adjustment rule or explain how an index would be used.
  • The parent Act and prior toll schedule were not supplied, so the exact change from current rates and the practical effect of repealing the discount cannot be verified.
  • The funded E-ZPass rates are described as minimums. The supplied text does not explain when or how a higher rate could be set.
  • The bill does not give a timeline or completion guarantee for the listed transportation projects.
  • It does not state the cost of issuing transponders or the future charge, if any, after the 210-day period.

Case for#

  • A possible argument for the bill is that it identifies projects for the next ten-year plan and sets out toll schedules to support turnpike projects and related costs.
  • Different rates by vehicle class and plaza make the scheduled charges specific rather than leaving all rates unstated in the bill.
  • The free-transponder period could make it easier for account holders to use the funded-account rate schedule.
  • The easements give New Boston a legal path to reconstruct the bridge while requiring compensation to the state.

Case against#

  • Toll users would face set rates from January 2027, but the supplied material does not show the previous rates or quantify the increase for each class.
  • The plan lists large project amounts, but the bill does not provide a full cost estimate or guarantee that the projects will be completed on schedule.
  • The stated periodic inflation-based toll review is not explained in the operative text supplied, leaving uncertainty about future rate changes.
  • The bill requires free transponders for a limited period but does not state what account or transponder costs may apply afterward.

Votes

4 recorded votes on this bill, newest first.

  1. Division No. 1725373

    Passed317 members voted

    Veto Override

    FOR · 292AGAINST · 25

    292For

    • Republican149
    • Democratic143

    25Against

    • Republican25

    67 members were paired and sat out the vote.

  2. Division No. 1661922

    Passed348 members voted

    Adopt Amendment

    FOR · 345AGAINST · 3

    345For

    • Republican186
    • Democratic159

    3Against

    • Republican2
    • Democratic1

    44 members were paired and sat out the vote.

  3. Division No. 1661923

    Defeated351 members voted

    Adopt Floor Amendment

    AGAINST · 305FOR · 46

    305Against

    • Republican178
    • Democratic127

    46For

    • Democratic33
    • Republican13

    41 members were paired and sat out the vote.

  4. Division No. 1661924

    Passed351 members voted

    OTPA

    FOR · 338AGAINST · 13

    338For

    • Republican187
    • Democratic151

    13Against

    • Democratic9
    • Republican4

    41 members were paired and sat out the vote.