Broadband projects streamlined by new Act

Summary#

Bill 93, the Getting Ontario Connected Act, 2022, amends the Building Broadband Faster Act, 2021 and the Ontario Underground Infrastructure Notification System Act, 2012. It creates new duties and powers to coordinate designated broadband construction and underground utility locates; its stated goal is to help get broadband projects built. The Act received Royal Assent, but some provisions require a later proclamation to take effect.

  • The Minister may require electricity distributors or transmitters to do work needed for a designated broadband project in specified circumstances. In some cases, a notice may modify an Ontario Energy Board order; a distributor or transmitter may ask a judge to move the notice’s deadline.
  • Municipalities must respond to certain broadband access applications within 10 or 15 business days. They must issue an approval with conditions they consider appropriate, or identify a material problem and give the applicant a chance to address it.
  • Listed utility owners and operators must provide requested infrastructure data near a designated broadband project within 15 business days. The Minister may use the Broadband One Window platform to request it; the data may only be used to enable project construction.
  • The underground-locate law sets response deadlines, creates a dedicated-locator process for certain projects, and assigns the project owner the locator’s cost.
  • The Minister gains powers over the Ontario One Call Corporation’s board, including appointing directors who cannot be a majority. The Minister and Corporation must have a memorandum of understanding about governance and other matters.

What it means for you#

  • Broadband project proponents: For covered projects, you must notify Ontario One Call at least 90 days before excavation is expected to start. The Corporation may allow less notice; for designated broadband projects, the Minister of Infrastructure can direct it to do so. The proponent and affected members must generally agree in writing on a dedicated locator within 10 business days. The project owner pays that locator.
  • Municipalities: You must review covered applications and respond within 10 business days for access involving 30 kilometres or less, or 15 business days for more than 30 kilometres. These limits count the proponent’s other proposed projects in that municipality too. The law does not require approval if there is a material deficiency or issue.
  • Utility members and excavators: Members generally must respond to standard locate requests within five business days and emergency requests within two hours, subject to exceptions. Locates generally last 60 days, but expire sooner if ground markings are no longer visible. Excavators must not submit standard requests more than 30 days before work is expected to start, and must not dig in a way they know or reasonably should know would damage or interfere with infrastructure.
  • People who submit locate requests: The Corporation cannot charge you a fee for submitting a request. The law also allows compensation claims in specified cases when a member or excavator causes certain losses.
  • General public: The Corporation must publish information about members’ locate performance. The Act also creates offences with fines, but some related provisions—including the new administrative-penalty system—require proclamation before they take effect.

Money#

No publicly available information on total public implementation costs is included in the supplied material.

  • The project owner must pay for a dedicated locator.
  • The Corporation cannot charge a fee to someone submitting a locate request. Regulations may set fees paid by Corporation members.
  • The Act allows compensation claims in specified circumstances, but gives no estimate of likely claims or payments.
  • The administrative-penalty provisions allow penalties up to $10,000, but have not taken effect unless proclaimed; the supplied material gives no expected revenue or cost.

What is unclear#

  • The supplied material does not give a proclamation date for the provisions that require one.
  • Regulations may set additional requirements, time limits, exemptions and penalty details. Those rules are not included here.
  • The bill does not set out all application procedures or explain how terms such as “material issue” will be applied.
  • No estimate is given for the cost to municipalities, the Corporation or other affected parties.
  • The parent Acts’ full prior text was not supplied, so the exact difference from all current-law requirements could not be checked.

Case for#

  • The bill could make broadband construction easier to coordinate by setting response deadlines for municipalities and utility owners.
  • Sharing infrastructure data could help project planners identify underground works near a proposed project.
  • Dedicated locators and locate deadlines could give project owners a clearer process before excavation.
  • Public performance information and compensation rules could encourage timely and accurate locates.

Case against#

  • One concern is that short municipal response deadlines may be difficult to meet for complex applications, and the bill does not explain how disputes over deficiencies will be resolved.
  • The Minister can require some utility work and, in prescribed circumstances, modify an Ontario Energy Board order. The bill’s limits and oversight for these powers are not fully clear from the supplied material.
  • The Minister may request a broad range of infrastructure-related data, including information the Minister considers necessary. The bill limits its use to enabling designated broadband construction, but the supplied material does not explain data-security rules.
  • Dedicated locators add a project cost, and the bill does not say how much they may cost or how disagreements over their selection will be settled.