New Data Center Approvals Would Pause

Summary#

HB 1515 would add a new section to the Code of Virginia to temporarily limit local approval of applications for siting new data centers. The title describes a temporary moratorium; the bill text does not state a separate policy goal. It is listed as introduced and continued from the last session, so it is not law.

  • Until the moratorium ends, a locality could not give final approval to a rezoning, special exception, special use permit, site plan, or plan of development for siting a new data center.
  • The limit would end on whichever happens first: all pending requests for interconnection to distribution service by electric utility customers that are data centers are fulfilled, or July 1, 2028.
  • The bill uses the definition of “data center” in another section of the Code. That definition is not included in the supplied material.

What it means for you#

  • Local governments: They would be barred from giving the listed final approvals for a new data center during the moratorium. The bill does not bar submitting applications or say whether earlier steps in the approval process may continue.
  • Data center developers: They could not receive those final local approvals during the moratorium. The bill does not directly prohibit building or operating existing data centers.
  • Electric utilities and data center customers: The bill makes fulfillment of pending interconnection requests one possible end point, but does not require utilities to fulfill requests by a set date.
  • Residents and other businesses: The bill does not directly change utility service, taxes, or approval rules for projects other than the listed approvals for siting new data centers.

Money#

No cost information is in the available material.

  • The bill does not state an appropriation, fee, fine, or staffing requirement.
  • It does not estimate costs or savings for local governments, utilities, developers, or the state.

What is unclear#

  • The supplied material does not include the Code’s definition of “data center,” so the full range of facilities covered cannot be verified.
  • “All pending requests” does not specify whether it means requests statewide or another group of requests.
  • The bill does not set rules for applications already under review, appeals, or local decisions made before the moratorium starts.
  • It does not say whether localities may continue preliminary review or grant approvals not listed in the bill.
  • The text does not explain how the moratorium would interact with other local or state approval requirements.

Case for#

  • A possible argument for the bill is that pausing final local approvals could give time for pending data-center electricity interconnection requests to be fulfilled.
  • The bill sets a latest end date—July 1, 2028—so the limit would not continue indefinitely if the requests remain pending.
  • It applies to final approvals for new data centers, rather than directly restricting existing facilities.

Case against#

  • The bill could delay new data-center projects even where a locality is ready to approve them; it does not provide exceptions.
  • The end date depends partly on an event the bill does not require utilities to bring about: fulfillment of the pending interconnection requests.
  • The bill does not explain which requests count, how their fulfillment would be confirmed, or how localities should handle applications already in progress.