Wind and solar moratorium pauses new projects

Summary#

SF-183, “Moratorium-solar and wind projects,” failed and did not become law. It would have created a new article in Wyoming law and amended provisions in several other statutes; the supplied material does not include those parent laws, so their current wording and the exact changes to them could not be verified. Its stated subject is public health and safety; its main change would have been to bar certain new or expanded wind and solar projects until June 30, 2030.

  • The ban would apply to a person starting or expanding a wind or solar energy facility project in Wyoming. Net metering systems are excluded.
  • Projects that began the local or state permitting process before the bill took effect would not be prohibited by the bill.
  • The bill would make several existing county and state permitting provisions subject to the moratorium. It does not set up a new permitting process.
  • It would also restrict use of eminent-domain authority for wind project collector systems, with an exception for a public utility holding a certificate of public convenience and necessity. The amended text would set June 30, 2030 as an end date for that restriction.
  • The moratorium and the new article would end June 30, 2030, unless the legislature took further action.

What it means for you#

  • Wind and solar project developers: If the bill had become law, you could not start or expand a covered project after it took effect, except where the permitting-process exemption applies. The bill does not require existing facilities to close.
  • Developers already in permitting: A project that had begun local or state permitting before the effective date would not be prohibited by this bill.
  • County and state agencies: The bill would make several existing permitting and siting rules subject to the moratorium. It does not specify a new agency, application process, enforcement process, or service for the public.
  • Landowners and project developers: The bill would restrict some use of eminent domain for wind collector systems, except by a public utility with the specified certificate. The text describes collector systems as infrastructure such as conductors, towers and substations that deliver power from a wind facility, up to but not including certain transmission-line substations or interconnections.

Money#

No cost information is in the available material.

  • The bill does not state an appropriation, fee, fine, staffing level, or cost estimate.
  • It does not say what costs agencies or project developers might face to apply or enforce the moratorium.

What is unclear#

  • The bill uses definitions from other Wyoming statutes, but those definitions are not supplied here. The full reach of “solar energy facility” and “wind energy facility” could not be checked.
  • The bill does not define “project” or explain when an expansion counts as a project initiated after the effective date.
  • It does not describe who would enforce the prohibition or what penalty, if any, would apply.
  • The bill does not explain how the moratorium would interact with permits or other approvals already issued, apart from protecting projects that had begun the permitting process before the effective date.
  • The supplied material does not include the amended laws’ current wording. The exact change to the eminent-domain restriction, and whether other amended provisions already have similar limits, could not be verified.

Case for#

  • The bill appears intended to pause new or expanded wind and solar facility projects for a set period, while allowing projects already in the permitting process to continue.
  • A temporary pause could give the legislature time to consider the effects of these projects before allowing more to begin.
  • The bill sets an end date for the moratorium rather than making the prohibition permanent.

Case against#

  • A broad ban on starting or expanding covered projects could prevent projects even where local or state permits might otherwise be available.
  • The bill does not explain how “project” or “expansion” would be applied, which could make it hard for developers and agencies to know which activities are prohibited.
  • The bill does not specify enforcement, penalties, or how agencies should handle affected proposals.
  • The bill would also restrict eminent-domain authority for wind collector systems, but the supplied text is not enough to verify how much of that restriction would be new.

Votes

The recorded vote on this bill, member by member.

  1. Division No. 1478669

    Defeated5 members voted

    S07 - Corporations:Do Pass Failed 2-3-0-0-0

    AGAINST · 3FOR · 2

    Each dot is one member. Hover or tap one to see who.

    3Against

    • Republican3

    2For

    • Republican2