Adjacent parcels exempt from 5-megawatt cap

Summary#

HB 1607 would amend Maryland’s Public Utilities Article, which governs the Community Solar Energy Generating Systems Program run by the Public Service Commission. Its stated goal is to remove limits based on the combined capacity of systems on adjacent parcels. The bill is introduced, not law; if enacted, it would take effect October 1, 2026.

  • Under current wording shown in the bill, systems on the same or adjacent parcels are generally subject to a combined 5-megawatt limit. The bill would apply that limit only to systems on the same parcel.
  • The bill would also remove adjacent parcels from the calculation for an existing exception that allows up to 10 megawatts on one parcel if certain conditions are met: at least 75% of capacity serves low- or moderate-income subscribers, or the systems meet specified agrivoltaics conditions.
  • Existing exceptions for certain locations—including rooftops, industrial-zoned land, brownfields, parking areas, airports, and some transportation rights-of-way—would remain.
  • The bill does not change the 5-megawatt limit for an individual community solar system or the program’s existing subscriber rules.

What it means for you#

  • Community solar developers and operators: Systems on adjacent parcels would no longer have to be combined to test the 5-megawatt location limit or the same-parcel exception. Systems on the same parcel would still be counted together. This could allow separate projects on neighboring parcels even when their combined capacity exceeds 5 megawatts.
  • Subscribers: The bill does not directly change how subscribers receive credits on their electricity bills or the existing low- and moderate-income rules.
  • Maryland Public Service Commission: The Commission’s duty to establish and maintain the program remains. The bill does not add a new agency or a new application, review, or approval process.
  • Property owners and the public: The bill does not require anyone to host a solar system or transfer land.

Money#

No publicly available information on the bill’s cost.

  • The supplied text includes no appropriation, fee, or staffing requirement.
  • Any costs to build or operate additional projects, or any effect on electricity bills, are not stated.

What is unclear#

  • The full current Public Utilities Article and Commission practices were not supplied, so other rules or guidance that may affect siting could not be checked.
  • The bill does not explain how parcel boundaries would be determined or how the Commission would apply the revised limit.
  • It does not estimate whether removing the adjacent-parcel limit would lead to more projects or what effects that might have.

Case for#

  • A possible argument for the bill is that separate parcels should not face a combined capacity limit simply because they are next to each other.
  • Removing the adjacent-parcel test could give developers more flexibility to plan projects across separate parcels, without changing the per-system 5-megawatt cap.
  • The bill keeps existing location exceptions and subscriber rules in place.

Case against#

  • One concern is that projects on neighboring parcels could add up to more than 5 megawatts without being counted together, even if they are part of a larger development.
  • The bill also means the existing 75% low- and moderate-income or agrivoltaics conditions for the 10-megawatt exception would apply to same-parcel projects, not projects split across adjacent parcels.
  • It is unclear how the Commission would distinguish separate projects from projects planned as one development.