Virtual power plant bill would create grid program

Summary#

HB 311, the Virtual Power Plant Act, would create a new law in Chapter 62 of New Mexico law; it does not amend an existing Act. Its stated goal is to let utilities and third parties combine customer and utility energy resources to provide services to the electric grid. The bill remains introduced and was postponed indefinitely, so it is not law and has not created a working program.

  • The Public Regulation Commission (PRC) must make rules by December 31, 2026, requiring covered electric public utilities to set up virtual power plant programs. The bill excludes electric cooperatives organized under the Rural Electric Cooperative Act.
  • Utilities must apply to the PRC by February 1, 2027. The PRC must approve, deny, or require changes to each application.
  • The rules must require utility tariffs (filed schedules of terms and charges) with technology-specific performance requirements and compensation. Owners or end-users must be allowed to lock in the compensation level in effect when the PRC approves the program for five years.
  • The PRC must set an initial program parameter at no less than 15% of peak demand for the first five years. The bill does not define what this parameter measures.
  • The rules must address data access, grid-event response, stakeholder input, utility and third-party aggregator fairness, and avoiding payment more than once for the same service.
  • Energy storage resources with usable capacity of one megawatt or more must meet wage and benefit requirements under the Public Works Minimum Wage Act to participate. Aggregators must file compliance affidavits.

What it means for you#

  • Electric utility customers: Utilities may recover reasonable program costs through cost-recovery methods approved by the PRC. The bill does not require customers to join a program or directly change household electricity rates.
  • Owners and end-users of energy resources: The bill would allow resources such as storage, electric vehicles, distributed generation, and demand-side measures to be aggregated for grid services. Participation is not required. If you participate, compensation and performance terms would be set through utility tariffs and PRC rules.
  • Owners or end-users of larger energy storage resources: To participate, resources with usable capacity of at least one megawatt must meet the named wage and benefit requirements. The bill does not state the applicable rates.
  • Utilities and aggregators: Utilities must apply and may run programs themselves; third parties may also aggregate resources. Aggregators must provide required affidavits, and the PRC may request more compliance information.
  • Cooperative utility customers: The bill’s definition of covered electric public utility excludes electric cooperatives, so it does not require those cooperatives to implement these programs.

Money#

No cost estimate is provided in the available material.

  • Utilities may recover reasonable implementation costs through PRC-approved methods. Recoverable costs include foundational, operating, information-technology, and operating-technology costs or investments.
  • The bill requires tariffs to provide performance-based compensation, but it does not set payment amounts.
  • No publicly available information on the total cost, staffing needs, or likely effect on customer bills.

What is unclear#

  • The bill does not define “initial virtual power program parameter,” “peak demand,” or “energy storage resource.” It is unclear exactly how the 15% minimum would apply.
  • The PRC must set program rules, but the bill does not itself set detailed enrollment, performance-measurement, payment, or appeal procedures.
  • The bill does not say how the wage and benefit requirements apply in detail to energy storage resources or what records would prove compliance.
  • It does not explain how the PRC should decide whether utility costs are reasonable, or how approved cost recovery would affect customer bills.
  • The bill does not specify when programs must begin operating or how the required five-year compensation lock-in works if program terms change.

Case for#

  • The bill appears intended to let many smaller energy resources work together to provide grid services, rather than treating each resource separately.
  • A possible argument for the bill is that those services could help avoid or delay investments in generation, transmission, or distribution. The bill directs the PRC to consider ways to maximize those potential benefits; it does not guarantee them.
  • Requiring compensation to reflect the full value of grid services could give owners a clearer basis for deciding whether to participate.
  • Rules on data access and utility-aggregator fairness could help make participation possible through third parties as well as utilities.

Case against#

  • One concern is that utilities may recover a broad range of program costs from customers, while the bill provides no cost estimate or specific test for deciding what costs are reasonable.
  • The 15% minimum is not clearly explained, so the PRC may have to decide what it measures and how to apply it.
  • The bill leaves important participation and payment details to later rules and utility applications. Until those are set, customers and resource owners cannot know the exact obligations or compensation.
  • The wage and benefit condition could limit participation by larger storage resources, but the bill does not explain how that condition will be applied.