Siting Priority for Mega Transmission Lines

Summary#

Wisconsin SB 1125 would amend the state energy policy in section 1.12 of Wisconsin law; it would not create a separate law or program. It failed, so it did not change current law. Its stated goal is to give certain routes first priority when siting very high-voltage transmission lines.

  • For a “mega transmission system”—a high-voltage line designed to operate above 400 kilovolts—the bill would give first priority to consolidated utility corridors, or to high-voltage direct-current systems or other underground facilities in specified existing corridors.
  • The specified locations are alongside an existing high-voltage transmission line, or within the right-of-way (land set aside for transportation use) of an interstate, U.S.-numbered or state trunk highway, or a railroad.
  • The legislative analysis says this priority would apply to the greatest extent feasible, consistent with economic and engineering considerations, electric-system reliability and environmental protection.
  • Current policy ranks existing utility corridors first, followed by highway and railroad corridors, certain recreational trails, and then new corridors. The bill would add a special priority for mega transmission systems.

What it means for you#

  • Electric utilities and project planners: If enacted, the bill would give the listed corridor options priority for mega transmission systems, subject to the qualifications described above. It does not set out an application, review or approval process.
  • People who live near possible routes: The bill would not itself approve a route, require a particular project, or change property ownership. It does not directly create a process for landowners to comment or appeal.
  • General public: Because the bill failed, the existing siting priorities remain unchanged.

Money#

No cost information is in the available material.

  • The bill does not include an appropriation, fee or fine.
  • The material does not estimate any costs for utilities, government, or the public.

What is unclear#

  • The bill does not define “consolidated utility corridors.”
  • The bill text does not explain how decision-makers would compare the listed priority routes or apply the feasibility and other qualifications described in the legislative analysis.
  • The supplied material does not show how the new priority would interact with other siting rules or approval processes.
  • The bill does not set out public notice, consultation, review or appeal steps.

Case for#

  • A possible argument for the bill is that giving priority to existing or shared corridors could limit the need to site very high-voltage lines in entirely new corridors.
  • Including underground options and high-voltage direct-current systems could give planners more route choices. The bill does not guarantee that those options would be used.
  • The stated qualifications leave room to consider cost, engineering, reliability and environmental protection.

Case against#

  • One concern is that the bill does not define “consolidated utility corridors,” leaving uncertainty about which routes qualify for the priority.
  • The bill does not explain how the new priority would fit with the existing order of priorities or how competing routes would be judged.
  • A possible trade-off is that prioritizing these options could narrow the routes considered first, though the stated qualifications mean it would not require their use in every case.