Large load customers face registration program

Summary#

SB 992, the Public Utilities – Large Load Customers – Registration and Demand Response Program bill, would add rules to Maryland’s Public Utilities Article and amend the Tax-General Article. It would require certain large electricity customers to register before connecting or expanding their connection, and require the Public Service Commission to create a demand response program. Its stated goal is to set registration, curtailment, and demand-response requirements for large load customers; it is introduced and is not law.

  • A “large load customer” would be a commercial or industrial retail electricity customer with actual or projected monthly demand of at least 25 megawatts and an actual or projected load factor above 80%. Water and sewage disposal companies are excluded.
  • The Commission would set the registration process. Customers would have to provide information about other connection requests, planned power sources, backup generation, water use and permits, site control, and financial commitments for needed transmission infrastructure.
  • The Commission would have to establish a demand response program. Participants would be offered a choice of 6 nonconsecutive four-hour periods or 10 nonconsecutive ten-hour periods each calendar year.
  • The bill would direct certain PJM curtailment orders and new-capacity costs to large load customers, and require financial security when a large load connection leads to a PJM order to procure new capacity.
  • A data center could qualify for the sales and use tax exemption through a new route if it registers, agrees to take part in the program, and either has enough on-site generation to fully operate or agrees to buy 100% renewable energy located in the PJM service territory.

What it means for you#

  • Large load customers: You would have to register with the Commission before interconnecting. The process would apply to new or expanded connections. The Commission may charge a reasonable registration fee.
  • Large load customers in the demand response program: The electric company would have to give 24 hours’ notice of a potential demand response period and 30 minutes’ notice before each period. The Commission must set compensation or incentives, penalties for nonperformance during force majeure events (events beyond a party’s control), a dispute process, and communication channels.
  • Large load customers building battery storage: A program participant building behind-the-meter energy storage would not need a certificate of public convenience and necessity or Commission approval under the cited provisions. The Commission would also set rules limiting how storage counts toward a customer’s load and when it can charge during peak demand.
  • Data centers: The new tax-qualification route would be separate from the existing investment-and-jobs route described in the bill. Under the existing route, a data center must make a specified investment and create at least five qualified positions within three years. The sales and use tax exemption covers qualified data center personal property, including listed computer, cooling, and electricity equipment.
  • Residential customers: When a large load connection causes PJM to order new capacity, the bill would require the related financial obligation to be passed to the large load customer and require financial security intended to protect residential customers from those costs. A PJM curtailment order assigned to an electric company serving large load customers would be passed only to those customers, except that electric companies could still act to maintain system reliability.
  • Electric companies and the Commission: The Commission would have to establish the registration process by January 1, 2027, and report on the registration program and demand response program each year starting by January 1, 2028. The bill would take effect July 1, 2026, if enacted.

Money#

No publicly available information on the bill’s estimated costs.

  • The Commission may charge a reasonable registration fee, but the bill sets no amount.
  • The Commission must set program compensation or incentives; the bill does not say who would pay them or how they would be funded.
  • The bill requires financial commitments for transmission infrastructure and financial security for certain new-capacity costs. It provides no estimates.
  • The bill gives no estimate of Commission staffing or other public costs.

What is unclear#

  • The Commission must set many registration and program details later, including the amount of financial security, how transmission costs are calculated, and how compensation and penalties work.
  • The bill does not define “load factor,” “substantially similar” connection request, or “force majeure” for these purposes.
  • It does not say how the Commission will decide whether a registration is complete beyond requiring certification within 30 days after receiving the required information. It allows the Commission to extend time frames if information is incomplete.
  • The bill requires access to utility-collected planning information while maintaining confidentiality, but does not describe how confidentiality will be protected.
  • The supplied material does not include the full current Public Utilities Article, so the bill’s overlap with existing Commission rules and powers cannot be fully checked.

Case for#

  • The bill appears intended to make large electricity projects disclose key plans—including power, water, and competing connection requests—before connecting to the grid.
  • Requiring financial commitments for needed transmission infrastructure could make large customers bear costs tied to serving their loads rather than leaving those costs with other customers.
  • The demand response program could give the Commission a way to call on participating customers to reduce or manage demand during specified periods.
  • The new data-center tax route links eligibility to registration, demand response participation, and a stated power-source condition.

Case against#

  • The bill leaves important rules to the Commission, so customers and the public cannot yet know the size of financial commitments, program payments, or penalties.
  • The required disclosures and transmission commitments could add costs or delay projects; the bill provides no estimate of those effects.
  • It is unclear how the Commission would separate costs caused by a large load from other grid costs, or how it would ensure residential customers are held harmless in practice.
  • The tax-exemption route permits either full on-site generation or an agreement to buy qualifying renewable energy, but the bill does not explain how compliance would be checked or how the two options would be treated.