Grid utilization plan targets efficiency gains

Summary#

“Grid Utilization” is an introduced bill that would amend North Carolina’s G.S. 62-110.1 and provide a one-time appropriation. Its stated goal is to improve electric-grid utilization; that is a goal, not a guaranteed result. The bill is not law, and passage is uncertain.

  • Each electric public utility would have to submit a grid-utilization report for Utilities Commission approval as part of its biennial integrated resource plan.
  • The report would assess transmission and distribution performance by substation, feeder, and transmission line, on annual and seasonal bases. It would also assess non-wires alternatives, including storage, customer-owned or customer-financed capacity, utility-owned distributed generation, and virtual power plants.
  • The Utilities Commission would issue a final order on the report, either with the resource plan or separately. The order would have to include any targets, timeframes, or other guidance the Commission considers necessary to improve utilization.
  • Each utility would have to submit proposed utilization metrics for approval. The bill names three: peak load compared with grid capacity; delivered load compared with potential deliverable load; and electricity lost in the distribution system.
  • The Commission’s order on the metrics would have to explain how they may inform future decisions on utility requests to recover costs for capital investments.

What it means for you#

  • Electric public utilities: They would have to prepare the report and submit proposed metrics for approval. The report must include a projected timeframe for plans to increase utilization. The bill does not expressly require utilities to complete particular improvements.
  • Utilities Commission: It would review the reports and metrics and issue orders. It could request other information for evaluating system performance and proposed improvements.
  • Customers and taxpayers: The bill does not directly change electricity rates, service, or customer eligibility. Metrics may inform future cost-recovery decisions, but the bill does not dictate the outcome of those decisions.

Money#

The bill appropriates $10,000 in nonrecurring General Fund money to the Utilities Commission for fiscal year 2026–27.

  • No estimate is provided for the utilities’ reporting costs, the Commission’s total implementation costs, or any savings or rate effects. No publicly available information.
  • The bill does not set a new fee or change how much utilities may recover for capital investments.

What is unclear#

  • The supplied material does not include the current text of G.S. 62-110.1, so it is not possible to verify what the existing resource-planning requirements are or exactly how much this bill would add.
  • The bill does not define “grid utilization,” “optimal utilization,” or the methods utilities must use to calculate the metrics.
  • It does not set a specific performance target or explain how the Commission should weigh the metrics in future cost-recovery decisions.
  • The bill’s metric-submission deadline is November 1, 2026, and its appropriation would start July 1, 2026. Both dates have passed. If the bill were enacted later, how those dates would apply is unclear.

Case for#

  • The bill could give the Commission and utilities a more detailed picture of how well existing grid assets are being used.
  • Assessing storage, distributed generation, and other non-wires alternatives could help compare options for improving utilization.
  • Standard metrics could give the Commission information to consider when reviewing future requests to recover capital-investment costs.

Case against#

  • The bill leaves key terms and calculation methods open, so utilities’ reports may not be comparable without further rules.
  • It requires reports and Commission orders but does not specify particular improvements utilities must carry out or how success would be measured.
  • The Commission must say how the metrics may inform future cost-recovery reviews, but the bill does not say how much weight the metrics must receive.
  • The $10,000 appropriation is specified, but the bill gives no estimate of the full cost of the reporting and review work.